5.1 Screen connection

An earth current loop is created if a wire or screen is connected between two earth points,
which are at different potential (voltage). If the instructions are followed correctly, then the
preamplifier and controller screen will only be connected to earth at one end.
Note: The PA20 earth terminal is a functional earth rather than a protective earth.
A protective earth provides protection from electric shock under a single fault condition. This
product has a double insulation and therefore does not require a protective earth.
A functional earth is used in order for the product to operate. In this application, the earth
(tank /boiler shell) is used as the common of the probe / preamplifier. It also provides a sink /drain
for any electrical interference.
Ensure that the screen is connected to the earth terminal of the PA20 and to the common
terminal of the controller.
Ensure the common terminal of the controller is not internally earthed. (All Spirax Sarco boiler
controls are internally isolated from earth).
The common terminal of the controller must only be earthed via the PA20.

CAUTION:
Do not connect the common terminal to an earth local to the controller. To do so may
induce an earth current loop, which may reduce the performance or damage the
product.

5. Wiring diagrams

Archive

Summary of Contents for LC2300

Page 1: ...e Instructions IM P402 72 AB Issue 6 4025350 6 1 General safety information 2 General product information 3 Installation 4 Setting up the controller 5 Wiring diagrams 6 Commissioning 7 Maintenance 8 F...

Page 2: ...em An independent high water alarm system must be fitted if it is considered a safety requirement In this case the relays must simultaneously isolate the feedwater supply and the boiler heat supply at...

Page 3: ...ut current is greater than 50 i e above the set point output current The amber LED 100 0 Indicates that the output is greater than 20 mA or less than 0 4 mA A three stage wave filter gives an averaged...

Page 4: ...ntain the integrity of the approval Maximum power consumption 6 VA 0 2 V Input 1 0 6 V Selectable inputs 0 20 mA 4 20 mA Input 2 opposite sense to input 1 0 20 mA 4 20 mA Note See separate literature...

Page 5: ...nt For the US and Canadian markets the controller must be wired in accordance with the National and Local Electrical Code NEC or Canadian Electrical Code CEC The controller and all connected circuits...

Page 6: ...switches to the positions shown in Figure 3 for the chosen functions Replace the printed circuit board Ensure that the LEDs engage with the holes in the front panel Replace the rear cover panel Note t...

Page 7: ...aves and high turbulence may otherwise cause continuous oscillation of the output signal giving over frequent valve movement The unit is supplied set to Filter 1 position the least damped response wit...

Page 8: ...earth A functional earth is used in order for the product to operate In this application the earth tank boiler shell is used as the common of the probe preamplifier It also provides a sink drain for a...

Page 9: ...rown Red Black LC2300 controller Screen Screen Fig 4 5 2 Wiring diagram standard version 4 20 mA Test Connect ammeter between Terminals 5 and 6 Do not disconnect loop This earth terminal is internally...

Page 10: ...ng to a 4 20 mA level transducer The controller can be connected to a self powered or loop powered 4 20 mA level transducer instead of a capacitance probe Connect wiring as shown in the Figures 6 and...

Page 11: ...are shown Wiring connections for other Spirax Sarco controllers transmitters are different and are given in the individual Installation and Maintenance Instructions Fig 8 Capacitance probe source Fig...

Page 12: ...g or maintenance of the controller is necessary Boiler water level controls and level alarms however do require testing and inspection General guidance is given in the UK Health and Safety Executive G...

Reviews: