SpectraLink 6300 MCU: Facility Preparation
PN: 1725-36122-001_N.doc
10
Installation Steps and Responsibilities
Task
Description
Wire
Contractor or
Electrician
Field Service
Engineer
Customer
Project Mgr/
Sys Admin
Site Preparation
Required materials provided by customer
Prepare location and arrangement of
shelves
Prepare –48V power for shelves
Run cables to Base Stations
Terminate cables at Base Stations
Prepare and install demarc blocks
Program Telephone System ports
Connect cables from Base Stations and
phone lines to demarc blocks
Wire demarc blocks for Interface Modules
Install Shelves and Interface Modules
Survey site and check components
Install shelves
Install junction panel
Connect power to shelves
Install cards in shelves
Connect junction panel
Connect demarc blocks to Interface
Modules
Install Base Stations
Install Base Stations in ceilings
Install Outdoor Base Stations
Check system diagnostics
Initialize System
Program handset features
Test System and Certify Site