26
Spearhead XRHD
250/270/300
8
After the job done
After the job done disconnect the PTO shaft, lift the machine and
transport it onto the appropriate place.
During transport reduce the speed, especially on bumpy
roads. The weight of the machine may render driving
difficult and damage the machine itself. During transport
the machine must be always in the central position.
PTO shaft must be disconnected during transport.
At disconnecting the machine respect the warning rules for
attaching the machine.
Store the machine on a dry and flat ground to avoid any damage or
corrosion.
8.1 Cleaning
To avoid any corrosion clean the machine after each working day,
especially working tools, bearings etc. Be careful to avoid damaging
hydraulic pipes, hydraulic cylinder, bearings and paint.