35
Note: Refer to Figure 31 for String Fuse Locations.
1.
Gripping only the plastic tab on top of the fuse extractor, pull straight upwards without
touching the fuse’s metal end caps or fuse-holder clips on printed circuit board.
2.
Away from open wiring box compartment, open the fuse extractor door and tilt fuse
extractor downward with a hand underneath to catch fuse as it slides out of fuse extractor.
3.
Next place the replacement fuse into fuse extractor and tilt upward to keep fuse from
dropping out. Close the fuse extractor door.
4.
With fuse/fuse extractor parallel to empty fuse position, lower fuse extractor while aligning
fuse caps with open fuse clips. Then push downward until the fuse snaps into the clips.
Follow the same procedure for replacing string fuses.
4.8.6
Inverter AC output wire connections
– Read all of the instructions, cautions, and warnings for the
Solectria PVI Inverter and associated PV array documentati
on.
– Installation and commissioning must be performed by a
licensed electrician in accordance with local, state, and
National Electrical Code ANSI/NFPA 70 requirements.
– Ensure no live voltages are present on PV input and AC
output circuits, and verify that the DC disconnect, AC
disconnect, and dedicated AC branch circuit breaker are in
the “OFF” position, before inverter installation.
– Verify that the dedicated 2-pole 240 Vac / 208 Vac circuit
breaker in the building electrical service panel is turned-off.
WARNING!
AVERTISSEMENT!
INFORMATION!
INFORMATIONS!
All screw terminals accept solid or stranded copper 14 – 6 AWG
wire only. A 3/16“ (4 mm) flat blade cabinet screw driver is recom
-
mended for tightening screw terminals to a 10.5 in-lbs (1.2 Nm)
torque.