8778002 

Released January 

8

 201

8

I.

 

DISPENSER INSTALLATION INSTRUCTION 

1. Install Directly into the Wall – Use Cover Panel

Hardware provided with the dispenser: 

o

Key

o

(4) Screws #10 x 1”L, Phillips Head

o

(4) Wall Anchors

Tools and materials required (not provided): 

-

 

Stud Finder 

-

 

Pencil 

-

 

Tape Measure 

-

 

Level 

-

 

Knife or Saw (to cut drywall) 

-

 

Powered Screwdriver with Phillips Head and 1/4" Hex Head Drive 

-

 

Cotton Gloves 

-

 

(2) Studs 2” x 4” x 12”L  

-

 

(6) Screws #10 x 1 1/2”L, Phillips Head 

Step 1: Dispenser Location 

Determine the location of the dispenser to be mounted. Ensure there will be 

no interference during the opening and closing of the cover or when paper is 

dispensed at the bottom of the dispenser. 

Step 2: Studs’ Location 

Use a Stud Finder to find the location of the two studs on both sides of the 

area where the dispenser will be mounted. Mark the locations of the studs. 

Step 3: Cut the Opening on Drywall 

Knowing the studs’ location, the dispenser should be mounted roughly in the 

middle, between the two studs. The bottom of the dispenser should be 48 

inches from the floor.  

To install the dispenser into the wall, it is required to cut an opening of 

10 5/8” W x 15 1/8”L  on the drywall.  

Recommend to use a pencil outlining the opening before cutting into the 

drywall: 

-

 

Using a tape measure, place a mark of 48” from the floor. Then use a 

level to draw a horizontal line from the mark. This is the bottom line 

of the opening. 

-

 

Using a tape measure, place a mark of 15 1/8” from the bottom line 

drawn from the last step. Then use a level to draw a horizontal line 

from the mark. This is the top line of the opening. 

-

 

Use the level to draw two vertical lines to connect the top and 

bottom lines. These two lines should be 10 5/8” apart from each 

other. These two lines should be roughly in the middle, between the 

two studs. 

Now use a knife or a saw to carefully cut the opening out of the drywall. 

See Figure 1 for more details. 

10 5/8"

15 1

/8"

48

"

Floor

Figure 1.

Summary of Contents for LOCOR

Page 1: ...an opening of 10 5 8 Width x 15 1 8 Length x 4 Depth TABLE OF CONTENT I Dispenser Installation Instruction Page 2 1 Install Directly into the Wall Using Cover Panel Page 2 2 Install into Existing Recessed Cabinets on the Wall Using Filler Panels Page 4 2a Use Insert Filler Panel Page 5 2b Use Hanging Filler Panel Page 5 II Changing Mounting Side of Cover Page 7 III Roll Support Installation Page 8...

Page 2: ...ut the Opening on Drywall Knowing the studs location the dispenser should be mounted roughly in the middle between the two studs The bottom of the dispenser should be 48 inches from the floor To install the dispenser into the wall it is required to cut an opening of 10 5 8 W x 15 1 8 L on the drywall Recommend to use a pencil outlining the opening before cutting into the drywall Using a tape measu...

Page 3: ...ton glove on the one hand that is used to hold the panel to avoid finger prints The other hand that is used to peel the film will not need glove Carefully place the dispenser into the big opening on the panel Then install the assembly of the cover and the panel together into the opening on the wall Slide the dispenser all the way in ensure there is no gap between the panel and the wall Use the key...

Page 4: ...the cabinet If the existing dispenser is secured by nuts use the appropriate socket to loosen the nuts to remove the dispenser out of the unit If the existing dispenser has the cover riveted or spot welded to the recessed cabinet use the power drill with the 1 8 drill bit to drill out the rivets and spot welds inside of the dispenser Then carefully use a hammer and a chisel to separate the hinge s...

Page 5: ...of the panel to secure the panel to the cabinet 5 Figure 6 b Use Hanging Filler Panel Hardware provided with the Hanging Filler Panel o 4 Screws 6 x 1 1 4 L Phillips Head o 3 Double Sided Tape Strips Remove the protecting film on the outside of the panel Recommend to put the cotton glove on the one hand that is used to hold the panel to avoid finger prints The other hand that is used to peel the f...

Page 6: ...s to secure the dispenser Option 1 Drive the four 10 screws provided into the mounting holes on the back of the dispenser to secure the dispenser to the cabinet Caution Note The length of the 10 screws is 1 inch which may be longer than the thickness of the drywall on the back of the cabinet If it is not acceptable please use option 2 Option 2 Drive the four 6 screws provided into the front mounti...

Page 7: ... 4 Remove the Lock First remove the screws Then remove the lock Step 5 Reverse steps 1 4 and switch side when install the components back on the cover Note that the Hinges and Pins should be installed on the same side that the cover is desired to be mounted on The Lock should be installed on the opposite side of the Hinges And the Plug should be installed on the same side as the Hinges See Figure ...

Page 8: ...identifying the paper roll width install the Roll Supports from the supplied kit included with the package Two Roll Supports Four Screws Roll Support Installation Instruction Sheet 7 WIDTH ROLL SUPPORTS 8 WIDTH ROLL SUPPORTS 8778002 Released January 8 2018 8 III ROLL SUPPORTS INSTALLATION Note Need to use a Phillips Head Screwdriver for the installtion Use four screws provided to install the Roll ...

Page 9: ...r cover for further examination If the assist wheel gets stuck do not force it to turn Open the dispenser cover for further examination b If the dispenser performs poorly not cutting or only partially cutting paper open the dispenser cover for further examination Check to ensure that paper roll is loaded correctly Check to ensure that the Roll Supports are installed at the correct places Re load t...