MASTERYS IP+
40-60 kVA 3/1
ENGLISH
IOMMASIPXX07-GB 02
27
7
OPERATING PROCEDURES
The operating modes to activate and manage the UPS are defi ned
in this chapter; please also refer to chapters 6 “Mimic panel” and 8
“Menus”.
For UPSs in parallel 1+1 redundant confi guration:
• Carry out the procedures on all the UPSs before going
on to the next operation.
• All procedures should be carried out on all the UPSs
within 30 seconds.
• The mimic panel operations are carried out on the “LEFT”
UPS with transformer confi gured as concentrator. Be
sure to operate on the SYSTEM menu.
7.1 START-UP IN NORMAL MODE.
• Check that all UPS and external battery switches are in position
0
(open);
• Supply the mains and auxiliary mains to the UPS;
• Put switch
Q2
into position
1
(mains ON);
• Wait for the mimic panel to switch on;
• Activate the procedure
COMMANDS
>
IMMEDIATE COMMANDS
>
START PROCEDURE
;
• Carry out the operations indicated on the mimic panel.
7.2 SHUTDOWN.
Shutdown interrupts the power supply to the load and causes the UPS and the battery charger to stop.
• Activate the procedure
COMMANDS
>
IMMEDIATE COMMANDS
>
STOP PROCEDURE
;
• Wait approx. 2 minutes for the UPS to shut down (the controlled shutdown of any servers is managed with
shutdown software);
• Carry out the operations indicated on the mimic panel.
7.3 EXTENDED OUT OF SERVICE.
If the UPS is deactivated for some time, the batteries must be recharged regularly; they should be recharged
every three months.
• Supply the mains and auxiliary mains to the UPS;
• Put switch
Q2
into position
1
(mains ON);
• Wait for the mimic panel to switch on;
• Activate the procedure
COMMANDS
>
IMMEDIATE COMMANDS
>
START PROCEDURE
;
• Put the external battery disconnectors into position 1 (battery circuit closed).
• Put or keep switches
Q3
and
Q5
in position
0
(inverter in output OFF and bypass OFF).
• The battery must be charged for at least ten hours.
• Once ten hours have elapsed, carry out the
STOP PROCEDURE
to deactivate the UPS.
7-1
Q3
Q5
Q4
Q2
Summary of Contents for MASTERYS IP+
Page 1: ...INSTALLATION AND OPERATING MANUAL MASTERYS IP 40 60 kVA 3 1...
Page 2: ......
Page 52: ......
Page 53: ...PARALLEL 1 1 REDUNDANT CONFIGURATION MASTERYS IP 40 60 kVA 3 1...
Page 57: ......
Page 58: ......
Page 59: ......