background image

 

 

 

 

 

BEFORE YOU START:

 

 

• 

Read all instructions carefully

 

• 

Identify all parts and check quantities against parts list

 

• 

Select a level site

 

• 

Do not mark cladding with pencil as lead can cause corrosion to cladding

 

• 

During assembly, ensure all drill filings are removed between  layers of steel, before riveting together

 

 

 

SAFETY:

 

 

• 

Do not attempt to build your shed in high winds

 

• 

Beware of sharp edges, we recommend that you use gloves

 

• 

Protect your eyes and ears

 

• 

For ease of assembly, use a friend to help 

 

 

 

TOOLS REQUIRED:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

WARRANTY REQUIREMENTS

:

 

 

 

Following are the minimum requirements for cladding used in Smart store Sheds.

 

 

• 

Wash all surfaces annually using a hose and soft nylon brush.

 

• 

Within 2 km of coast –

 

wash every 3 months as above. After a storm, wash the cladding and the gutters as soon 

as possible to remove any highly corrosive salt deposits.

 

• 

Volcanic Ash Fallout –

 

wash as soon as possible, removing fall out from roof and gutters.

 

• 

Do not allow manures, chemicals or other corrosive materials to have direct contact with cladding

.

 

CONGRATULATIONS ON PURCHASING A DURATUF SMART STORE SHED. 

 

BEFORE YOU BEGIN THE ASSEMBLY PLEASE NOTE SOME IMPORTANT POINTS:

 

2

 

DRILL

 

RIVETER

 

3.5mm DRILL BIT

 

HAMMER

 

LADDER

 

TAPE MEASURE

 

HEX DRIVE

 

NAIL PUNCH

 

SQUARE DRILL BIT

 

SKILL SAW 

 

(timber floor only)

 

Summary of Contents for SM3020

Page 1: ...ASSEMBLY INSTRUCTIONS SM3020 BASE SIZE 3 020m x 2 020m...

Page 2: ......

Page 3: ...ing are the minimum requirements for cladding used in Smart store Sheds Wash all surfaces annually using a hose and soft nylon brush Within 2 km of coast wash every 3 months as above After a storm was...

Page 4: ...de Wall Angle 1 980m 4 Roof 2 200m 6 Door Sheet Narrow 1 850m 3 Door Sides 1 850m 4 Door Jamb 1 890m 2 Door Brace 1 160m 2 Door Brace 0 915m 2 Double Door Weatherstrip 1 850m 1 Barge 1 102m 4 Ridge Ca...

Page 5: ...ON QTY DIAGRAM Front Back Bottom Plates H4 Green 3 020 m 2 Front Back Top Plate H1 Red 3 020 m 2 Side Wall Bottom Plates H4 Green 2 020 m 2 Side Wall Top Plates H1 Red 2 020 m 2 Ridge Beam 90 x 45 3 0...

Page 6: ...EMBLE DOOR QUICK OVERVIEW Door Sheets Padbolt Support Top Plate Back Side Wall Sheets Roof Sheets Top Plate Side Top Plate Front Bottom Plate Front Bottom Plate Side Back Wall Sheets Front Wall Sheets...

Page 7: ...ng through from underneath During construction you may raise the bottom timber plate to allow the wall cladding to protrude 20mm below the bottom plate This will stop water flowing between the bottom...

Page 8: ...or braces in posi tion as shown in fig 3 Ensure that the top and bottom ends of the braces are under the door flashings as shown in fig 4 and opposite ends of the braces overlap in the middle Rivet do...

Page 9: ...3 Nail wall sheets to the Top Plate at each end making sure that the top corners of the sheets are flush with the top of the Top Plate and that the sides of the wall sheet overhang the Top Plate by a...

Page 10: ...sing two clouts per pan STEP 4 Nail the wall sheets to the Bottom Plate at each end ensuring that each side of the wall sheets overhangs the Bottom Plate by 15mm and that the distance between the Top...

Page 11: ...eets are flush with the top of the Top Plate and that the sides of the wall sheets overhang the Top Plate by 15mm as shown Nail wall sheets to Top Plate two clouts per pan Nail the wall sheets to the...

Page 12: ...2 per join screw the Top and Bottom Plates together in the corners STEP 2 Repeat Step 1 with the second Side Panel ensuring that the Side Panel overlaps the Back Wall Panel STEP 3 Stand up the Front...

Page 13: ...nd use 2 x 75mm screws to secure the Jack Studs to the underside of the Ridge Beam one at each end fig 1 Turn the Ridge Beam Jack Stud assembly over and place it on the timber Top Plate in a central p...

Page 14: ...Clout predrill and nail Roof Sheet through the rib into the Top Plate b fig 2 Repeat at the front left hand IMPORTANT Use 50mm Clouts only on ribs covered by flashings shown in fig 2 Predrill holes us...

Page 15: ...ORROSION AND COULD THEREFORE VOID THE WARRANTY FIT PADBOLT Rivet Padbolt to door and keeper onto Door Jamb as shown 14 YOUR DURATUF SMART STORE SHED IS NOW COMPLETE RELAX FRONT BASE PLATE BACK BASE PL...

Page 16: ...s less than 200g m2 as published by Branz Warranty certificate being returned to manufacturer within 21 days of purchase together with proof of purchase This warranty does not cover the following Fast...