FOUNDATION

 

SMART STORE WOODEN FLOOR 

 

 

• 

The optional Smartstore kitset wooden floor is precut and de-
signed to be fitted into the shed after the shed is assembled.

 

 

 

• 

Assemble shed as per  instructions and fit floor last.

 

          (see page 13 for details). 

 

CONCRETE SLAB FOR RAISED BASE PLATE SHED

 

 

To build a raised concrete slab for your shed to sit on, we recom-

mend the following:

 

 

• 

The raised slab size should be 15mm smaller than the base 
size of the shed and at least 30mm above ground line.

 

 

• 

The slab should be 80mm thick in the middle and 100mm 
thick around the edges.

 

 

• 

The slab should be laid on a solid or compacted base.

 

 

• 

Plastic sheeting under slab will prevent moisture coming 
through from underneath

.

 

 

• 

During construction, you may raise the  bottom timber 
plate to allow the wall cladding to protrude 20mm below 
the bottom plate. This will stop water flowing between 
the bottom plate and the concrete floor. 

 

          

See note on page 8.

 

80mm

 

100mm

 

7.5mm

 

20mm

 

Concrete Floor

 

Base Plate

 

Wall Cladding

 

6

 

RAISED BASE PLATE OPTION

 

(For sheds placed on a raised concrete floor)

 

No doubt by now you will have decided what sort of base you are putting down. 

 

Please read the section that applies to your situation.

 

If you choose to pour a concrete base you will need to decide whether you wish to raise the base plate of your shed. 

This allows the cladding to protrude below the surface of the concrete and ensures a water tight pad. 

 

See concrete pad specifications below

 

By choosing this option you will need to make the concrete pad to the specification below.

 

Summary of Contents for SM1515

Page 1: ...ASSEMBLY INSTRUCTIONS SM1515 BASE SIZE 1 520m x 1 520m...

Page 2: ...cess needs to be adhered to to qualify for the steel warranty of your Duratuf Smart store shed Wash all surfaces annually using a hose and soft nylon brush Within 2 km of coast wash every 3 months as...

Page 3: ...Angle 1 905m 2 Roof 1 720m 3 Door Sheet Narrow 1 940m 2 Door Sides 1 940m 2 Door Jamb 1 980m 1 Corner Door Jamb 1 980m 1 Door Brace 1 200m 2 Barge 1 720m 2 Spouting 1 555m 1 Door Top Bottom 0 945m 2 H...

Page 4: ...TS LIST PACK 2 TIMBER PACK DESCRIPTION QTY DIAGRAM Front Back Bottom Plates H4 Green 1 520 m 2 Front Back Top Plate H1 Red 1 520 m 2 Side Wall Bottom Plates H4 Green 1 520 m 2 Side Wall Top Plates H1...

Page 5: ...DE PANELS 1 LAY FOUNDATION 2 ASSEMBLE DOOR QUICK OVERVIEW Top Plate Back Side Wall Sheets Barge Flashing Spouting Roof Sheets Top Plate Side Top Plate Front Bottom Plate Front Bottom Plate Side Back W...

Page 6: ...g through from underneath During construction you may raise the bottom timber plate to allow the wall cladding to protrude 20mm below the bottom plate This will stop water flowing between the bottom p...

Page 7: ...emble door as shown ensuring narrow face of flashing is on the front as per fig 1 STEP 4 On the back of the door place door braces in posi tion as shown in fig 4 Ensure that the top and bottom ends of...

Page 8: ...with bottom of sheets flush with each other Rivet sheets together on overlaps as shown STEP 3 Nail wall sheets to the Top Plate at each end making sure that the top of the sheets are flush with the t...

Page 9: ...th bottom of sheets flush with each other Rivet the sheets together on overlaps as shown STEP 3 Nail the wall sheets to the Top Plate at each end making sure that the top of the sheets are flush with...

Page 10: ...drill bit Check the distance between the top and bottom plates then use a further 2 x 30mm clouts to nail the Door Jamb Flashings to the bottom Plate Pre drill holes STEP 4 Place the door on the panel...

Page 11: ...panels while they are screwed together Before fixing ensure that the Side Panel overlaps the Back Panel as shown Using 2 x 40mm screws screw Top Plates together in the corner Using 2 x 40mm screws 2...

Page 12: ...x rivets per join STEP 2 Position the Roof Sheets with front overhang of 130mm at each end fig 1 Using 4 x 50mm Clouts predrill and nail the Roof Sheets to the Top Plates through the ribs at each cor...

Page 13: ...REMOVE ALL DRILL FILINGS FROM ROOF WALLS AND CHANNELS THOROUGHLY FAILURE TO DO THIS WILL RESULT IN CORROSION AND COULD THEREFORE VOID THE WARRANTY FIT PADBOLT Rivet Padbolt to door and keeper onto Doo...

Page 14: ...s less than 200g m2 as published by Branz Warranty certificate being returned to manufacturer within 21 days of purchase together with proof of purchase This warranty does not cover the following Fast...

Page 15: ......

Page 16: ......

Reviews: