Smappee EV Base
–
Installation manual - English
15
c.
The floor plate is now separated from the EV Base and charging cables can be removed from the
EV Base, together with the supplies
(concrete anchors, washers, cable ties,…)
.
Mount the anchors
a.
Use the floor plate to mark the position of the anchors on the pre-prepared concrete
foundation. Make sure the top side label of the floor plate is facing upwards. The power supply
cables and Ethernet cable should go through the central recess of the floor plate.
b.
Drill 4 holes of 12 mm diameter through the slots to a depth of 70 mm. Insert the supplied
concrete anchors. Make sure that there is approximately 3 cm of threaded wire visible above
ground level. Do not drill holes for the 4 remaining 5 mm slots.