Smappee EV Base 

 Installation manual - English 

 
 

16 

 

 

c.

 

Mount the floor plate over the anchors and make sure it is level in both directions. If not, tilt the 
floor plate until it becomes level. 
 

 

 

 

 

To tilt the floor plate, insert large washers below the floor plate until it becomes level. 
 

 

 

 

 

Summary of Contents for EVB-1332-BL-E

Page 1: ...English Version 1 4 January 2022 Smappee EV Base Installation manual ...

Page 2: ...glish 2 Table of contents 1 Introduction 3 2 Safety instructions 4 3 Models 6 4 Components 7 5 Technical specifications 8 6 Preparing the installation 11 7 Installation and activation 14 8 Using the EV Base 24 9 Declaration of conformity 28 ...

Page 3: ...n and enable you to use all the advanced features of this product to the full Support Only qualified electricians or equivalent may install the Smappee EV Base If you have any questions please contact your service partner Please have the following information ready to hand to speed up the process Article number and serial number which you can find on the identification label of the charging statio...

Page 4: ...tion is intended exclusively for charging electric vehicles and when installed correctly may be used by untrained individuals Switch off electrical power supply to your charging station before installation or maintenance work Do not use the charging station if damaged defective Do not immerse the charging station in water or any other liquids Do not expose the charging station to heat flame or ext...

Page 5: ...jects on the charging station Transport and storage Disconnect electrical power supply before removing the charging station for storage or relocation Only transport and store the charging station in its original packaging No liability for damage incurred will be accepted if the charging station is transported in non standard packaging Store the charging station in a dry environment within the temp...

Page 6: ... 2 x 22 kW Socket with shutter EVB 2332 C5 E 5425036932296 EV Base 3 phase 2 x 22 kW Type 2 cable 5m EVB 1332 BR E 5425036932302 EV Base 3 phase 1 x 22 kW Socket Right EVB 1332 BL E 5425036932319 EV Base 3 phase 1 x 22 kW Socket Left EVB 1332 C5R E 5425036932340 EV Base 3 phase 1 x 22 kW Type 2 cable 5m Right EVB 1332 C5L E 5425036932357 EV Base 3 phase 1 x 22 kW Type 2 cable 5m Left ...

Page 7: ...rging cable 7 2 x cable ties for strain relief 8 2 x M32 cable gland 9 2 x QR code for usage see Scan and charge page 26 10 1 x Quick Installation Guide Identification label The identification label of your charging station is located under the top cover of connector 1 1 Manufacturer 2 Article number 3 Rating 4 Manufacturing date 5 QR code containing article number and serial number 6 Serial numbe...

Page 8: ...sformer is required Grounding TN system PE wire TT system Independently installed ground electrode 100 Ohm spreading resistance IT system connected to a shared reference common earth with other metal parts Rated voltage Un 230 V 400 V Rated insulation voltage Ui of a circuit 500 V Rated impulse withstand voltage Uimp 4 kV Rated frequency fn 50 Hz 60 Hz Rated current Ina 32 A Rated current Inc of a...

Page 9: ...ee 3 Electrical safety class I Stand by use LED brightness 0 3 W LED brightness 100 18 W Environmental conditions Indoor and outdoor use Operating temperature 25 C to 40 C Storage temperature 25 C to 60 C Relative humidity 0 95 non condensing Maximum installation altitude 0 2 000 m Access Locations with restricted and non restricted access Physical properties Dimensions 1200 x 600 x 150 mm Weight ...

Page 10: ...ing current to decrease the internal temperature of the charging station This stabilises the internal temperature and makes it less likely that a transaction will be unexpectedly paused If the product is directly exposed to sunlight the automated temperature management may automatically start below the maximum ambient temperature Therefore wherever possible avoid exposing the charging station to d...

Page 11: ...er rating and distance between the meter cabinet and the charging station The voltage drop must not exceed 5 It is advisable to have a maximum voltage drop of 3 The maximum wire gauge that can be fitted is 6 mm in case of flexible conductors or 10 mm when solid conductors are used The power supply trajectory from the circuit breaker panel up to the EV Base charging station must be protected agains...

Page 12: ...mount A stable and level ground needs to be prepared in advance We advise a levelled concrete foundation at ground level It is also possible to have the foundation a little lower than ground level This allows the anchors to be masked and the EV Base to be integrated in the surrounding soil Depending on the subsoil the size may vary Please refer to the technical specifications of size and weight to...

Page 13: ...randed power supply cables Drill and rock drill diameter 12 mm 19 mm socket wrench with ratchet handle Hammer Supplies included 4 x concrete anchors Ø 12 mm x 100 mm 4 x washers Ø 50 mm 4 x M6 bolts and washers 2 x cable ties for strain relief 2 x M32 cable gland Supplies not included Ethernet cable or RJ45 connector for wired communication Power supply cables Ferrules 6 mm for stranded power supp...

Page 14: ...ut up caution tape and warning signs to mark the work areas Make sure no unauthorised people can enter the work areas CAUTION The charging station contains electric components that may still contain electrical charge after being disconnected Wait at least 10 seconds after disconnection before commencing work CAUTION Adaptors or conversion adaptors and cord extension sets are not allowed to be used...

Page 15: ...ition of the anchors on the pre prepared concrete foundation Make sure the top side label of the floor plate is facing upwards The power supply cables and Ethernet cable should go through the central recess of the floor plate b Drill 4 holes of 12 mm diameter through the slots to a depth of 70 mm Insert the supplied concrete anchors Make sure that there is approximately 3 cm of threaded wire visib...

Page 16: ...English 16 c Mount the floor plate over the anchors and make sure it is level in both directions If not tilt the floor plate until it becomes level To tilt the floor plate insert large washers below the floor plate until it becomes level ...

Page 17: ...otherwise for instance in the packaging of the EV Base b Position the EV Base on the floor plate c Position one of the four supplied large washers Ø 50 mm over each of the 2 front screw threads anchors d Place two nuts on the front screw threads and hand tighten Do NOT torque the nuts yet This is done in the last step of the installation when the back cover of the EV Base is in place ...

Page 18: ...ly cable to the correct terminal block indicated with L1 L2 L3 N and PE Phase rotation To avoid overloading the first phase with one phase electric vehicles phase rotation is recommended We recommend rotating the phases as shown in the table below EV Base Connector Phase mapping EV Base 1 Connector 1 L3 L2 L1 N as indicated on the label Connector 2 L1 L3 L2 N EV Base 2 Connector 1 L2 L1 L3 N Conne...

Page 19: ...ted to N and PE respectively EV charging cable mounting only fixed cable version This section is only relevant if the EV Base comes with a fixed cable If you have a socket version please continue to the next section a Mount the fixed charging cables through the M32 cable glands on the left and right side of the EV Base Mount the power supply wires to the terminal block Do not forget to connect the...

Page 20: ...rge as a way of charging If you won t use this method please continue to the next section The two supplied QR codes need to be put on top of the Smappee EV Base Fix the QR code near the corresponding connector to make sure the driver scans the correct QR code Switching on the EV Base a Check all connections are secure and power up both power supplies of the EV base b Check the status LEDs o Chargi...

Page 21: ...ultiple charging stations can be installed at a single location To add a new charging station in the mobile app go to Settings Your Smappee charging stations The settings of your charging station can be adjusted in the Smappee Mobile app or Dashboard Smappee Mobile App Name Minimum and maximum current per connector Charging speed per connector and LED brightness Dashboard Name Minimum and Maximum ...

Page 22: ...n loosen the anchor nuts to eliminate any torsion in the frame b Position one of the four supplied large washers Ø 50 mm over each of the 2 rear screw threads anchors c Place two nuts on the rear screw thread d Mount the 4 remaining M6 bolts and washers to secure the EV Base with the floor plate e Tighten all anchor nuts and bolts with a wrench ...

Page 23: ...Smappee EV Base Installation manual English 23 f Finish off by using the preferred top coat ...

Page 24: ...e different charging sequences Each EV Base that is installed and activated is Plug and charge Changing the Session Activation Method is done using the Smappee Dashboard Changing the authentication methods can be done remotely Scan and charge and Swipe and charge with Smappee CSMS can only be used when a Smappee Payment Agreement has been signed Please contact your Business Developer for more info...

Page 25: ...rdered via info smappeeservices com Public charging other EV drivers can use this charging station an pay with a payment card from a third party eMSP such as Shell Recharge or Plugsurfing This can be done through Smappee s own CSMS or through a third party CSMS In case you would like to use the Smappee CSMS please contact info smappeeservices com to activate this Split Billing This is aimed at emp...

Page 26: ...charging station and the app will guide them through the process of starting the charging session It is also possible to set discount rates for specific users Please contact info smappeeservices com to activate Scan and charge Start charging Stop charging More information on how to use the Smappee EV Wall Business can be found on support smappee com hc Smappee EV Line ...

Page 27: ...e and wait until the LED is green pulsing If no authorisation is required wait until the LED becomes green pulsing Blue flashing Your RFID card is being verified Wait until the LED is green pulsing Green pulsing The Smappee EV Base is charging your EV Your EV is being charged Green continuous The EV is now fully charged Disconnect the cable and put it back in its socket of the Smappee EV Base Red ...

Page 28: ...lowing documents Metering EN50470 1 2006 EN50470 3 2006 Emissions EN61326 1 2013 Radiated Emission EN 55011 2009 EN 55032 2015 Class B Conducted Emission EN 55011 2009 EN 55032 2015 Class B Harmonic current Emission EN 61000 3 2 2005 A1 2008 A2 2009 Flicker EN 61000 3 3 2008 Immunity EN61326 1 2013 ESD EN 61000 4 2 2008 EN 61000 4 2 2009 Radiated immunity EN 61000 4 3 2006 A1 2007 A2 2010 Power fr...

Reviews: