13 Decommissioning the Inverter
To decommission the inverter completely upon completion of its service life, proceed as described
in this Section.
Risk of injury when lifting the inverter, or if it is dropped
The inverter weighs 16 kg. There is risk of injury if the inverter is lifted incorrectly or dropped while
being transported or when attaching it to or removing it from the wall mounting bracket.
• Transport and lift the inverter carefully.
Procedure:
1.
Danger to life due to high voltages
• Disconnect the inverter from all voltage sources (see Section 10, page 60).
2.
Risk of burns due to hot enclosure parts
• Wait 30 minutes for the enclosure to cool down.
3. Unscrew the swivel nut from the threaded sleeve
for the network cable.
4. Unscrew and remove the threaded sleeve from
the network port thread on the inverter.
13 Decommissioning the Inverter
SMA Solar Technology AG
Operating Manual
85
SB30-50-1AV-40-BE-en-10
Summary of Contents for SUNNY BOY 3.0
Page 99: ......