This control can be programmed as follows:

1.

Outdoor reset:

The supply water temperature is 

automatically adjusted up or down based on outdoor 

temperature. The control automatically controls the 

number of modules required to maintain required supply 

water temperature.

2.

Setpoint temperature:

The control can be programmed 

to maintain a set supply water temperature. The control 

automatically controls the number of modules activated to 

maintain the setpoint temperature.

SC-9 Control

The SC-9 control allows up to 9 stages of operation for space

heating, domestic water or combination, in a Caravan system.

Generally each stage controls 1 module. However, it is possible to

have more than one module activated with each stage.

Standard programmable features include: 

system activation or

de-activation based on outdoor temperature; minimum target sup-

ply water temperature; adjustable design target supply water tem-

perature; adjustable delay between stages; adjustable 

outdoor and indoor design temperatures; delay to allow 

combustion air damper to open; ability to provide equal run time

rotation of boiler modules; fixed lead of a module when Caravan

system activates; first on/last off or first on/first off for modules;

control of primary circulator and periodic exercising of primary cir-

culator when system is inactive.

The view menu on the control includes error messages, actual

outdoor air temperature, actual supply water temperature, 

target water temperature, running time for each stage and the dif-

ference between supply water and return water 

temperatures.  

The SC-9 can be programmed as follows:

1.

Outdoor reset: 

The supply water temperature is 

automatically increased as outdoor temperature 

decreases and decreased as outdoor temperature 

increases. The control activates only the number of stages 

required to maintain the required supply water

temperature.

2.

Setpoint temperature:

The control maintains a set supply 

water temperature. The control activates only the number 

of stages required to maintain the setpoint temperature. 

Setpoint temperature may be used for a Caravan system 

that is dedicated for use as volume water heating.

3.

Domestic hot water:

The domestic hot water controls 

override the SC-9 control for only those modules used to 

heat the domestic hot water. The modules for domestic 

hot water are isolated from space heating system until 

demand for domestic hot water is satisfied. The modules 

not used for domestic hot water heating remain under 

control of SC-9 control.

Slant/Fin offers domestic hot water control packages and 

external tankless heaters as options for use with the SC-9 

control.

BILL OF MATERIALS FOR SC SERIES CONTROLLERS

Other Options include:

• Immersion well for supply water sensor: to be installed in control header supplied with Caravan

• High Limit (manual reset) and Immersion Well: to be installed in control header supplied with Caravan

• Low Water Cut-Off (manual reset): to be installed in modular boiler headers above modules cast iron heat exchanger

• Domestic Hot Water Control Packages: components include EMV valve; setpoint aquastat L6006A with immersion well. This is to 

be used with external heat exchanger such as Caravan BP series brazed plate heat exchangers.

Circulators, switches, wiring and other relays are provided by contractor.

Material List for SC-3

• SC-3 modular boiler control (part# 435-084)

• 1 Outdoor sensor (part # 339-070)

• 1 Universal sensor to be used as supply water sensor 

(part # 339-071)

• 1 Plastic tie strap

Material List for SC-9

• 1 SC-9 modular boiler control (part # 435-085)

• 1 Outdoor sensor (part # 339-070)

• 2 Universal sensors (part # 339-071)

-

1 to be used as supply water sensor

-

1 can be used as return water sensor

• 2 Plastic tie straps

Summary of Contents for CARAVAN GGHT-1050E

Page 1: ...al electri cal codes The unit must be electrically grounded if an external power source is used In Canada the installation must be in accordance with standards CGA B149 1 and B149 2 installation codes...

Page 2: ...394 1932 11202 1680 57 7 80 60 61 8 3660 301 16 665 8 10 1323 32 253 16 115 16 15 10 3 GGHT 2450E 7 GG 350HES 2450 1995 11571 1736 59 6 81 40 72 1 4270 301 16 671 8 9 1323 32 253 16 115 16 18 6 3 GGHT...

Page 3: ...3 Design Data Max ASME Working Pressure 100 psi Power Requirements 120 volts 60 HZ 34 amps per module Figure 1 Gas Caravan dimensions and typical piping hot water models...

Page 4: ...r piping for variable circulation Figure 3 Supply and return piping locations Figure 4 Instantaneous tankless coil two temperature with recirculation Figure 5 Storage tank from tankless coil with reci...

Page 5: ...cify 30 50 or 100 psi Control header unmounted one per system Draft hoods unmounted OPTIONAL EQUIPMENT Hot water supply and return header assemblies Control panel with automatic lead lag Spark ignitio...

Page 6: ...opening near the floor below burner air inlet and one louvered opening near the ceiling above the highest draft regulator each opening with a minimum FREE air passage area of 1 square inch per 4000 B...

Page 7: ...7 Figure 8 Typical layouts for gas fired systems...

Page 8: ...p obstruction A vent cap should be used where permitted for additional protection against adverse wind conditions and precipitation The National Board of Fire Underwriters recommend that the chimney s...

Page 9: ...Table 2a depicts the proper diameter Dim C of the connec tor rise depending upon its total length top of the draft hoods to the breeching above Based on single row of modules with no elbows NOTE For c...

Page 10: ...1 2 34 3 11 1 1 4 2 19 1 37 1 07 0 082 6 54 2 94 3 27 4 35 1 1 2 2 63 1 64 1 29 0 098 7 84 3 52 3 92 5 21 2 3 55 2 23 1 74 1 320 10 60 4 77 5 30 7 05 3 5 72 3 59 2 81 2 130 17 08 7 69 8 84 11 40 Model...

Page 11: ...ize only as many modules as the system load requires Only one stage cycles at a time The other stages remain off or operate continuously thereby performing at peak efficiency For example in a 10 modul...

Page 12: ...increases The control activates only the number of stages required to maintain the required supply water temperature 2 Setpoint temperature The control maintains a set supply water temperature The co...

Page 13: ...13 FIELD WIRING AT MODULES...

Page 14: ...14 SC 3 SYSTEM WIRING DIAGRAM...

Page 15: ...15 SC 3 LADDER WIRING DIAGRAM...

Page 16: ...16 SC 9 SPACE HEATING WIRING DIAGRAM...

Page 17: ...17 SC 9 SPACE HEATING LADDER WIRING DIAGRAM...

Page 18: ...18 SC 9 SPACE AND DOMESTIC HOT WATER WIRING DIAGRAM...

Page 19: ...19 SC 9 SPACE AND DOMESTIC HOT WATER LADDER WIRING DIAGRAM...

Page 20: ...stallation If any parts are found to be defective in material or workmanship Slant Fin will repair or replace the defective parts SECOND THROUGH TENTH YEAR LIMITED WARRANTY FOR CAST IRON SECTION ASSEM...

Page 21: ...bustion chamber tankless heater exhaust and air inlet pip ing burner enclosure mixing elbow gas and air orifice blower assembly air filter and electrical and mechanical components fur nished to Slant...

Page 22: ...22 NOTES...

Page 23: ...CARAVAN SYSTEM RATING PLATE System rating plate format for Caravan modular boiler system System rating plates are available upon request using the form on the back cover 23...

Page 24: ...s shipped with a rating plate bearing the model serial number capacities and certifications for that module A modular boiler system is a single boiler To meet local requirements a system rating plate...

Reviews: