Gas Main Sizing
To determine the correct pipe diameter for the gas main serving a specific Caravan
system, proceed as follows:
a. Follow the building plans, find total length of straight pipe between supply from gas
meter and boiler gas header.
b. Using data in Table 4, calculate equivalent linear length of screw pipe fittings used in
fabrications of main. Add this to figure from step (a) to obtain equivalent total length.
c. Find Caravan gas consumption in cubic feet per hour from Table 3 in hot water
systems.
d. Multiply the system total hourly gas consumption by flow correction value from
Table 5.
e. Locate system’s total equivalent pipe length in right column of Table 6.
f.
Move vertically to the system’s corrected flow rate calculated in step (c). If this value
falls between two of those listed, select larger value.
g. From this point move horizontally to the left column and read suggested pipe
diameter for gas main.
GGT-600E
600
GGHT-700E
700
GGHT-750E
750
GGHT-800E
798
GGT-900E
900
GGHT-1050E
1050
GGHT-1125E
1125
GGHT-1200E
1197
GGT-1200E
1200
GGHT-1400E
1400
GGHT-1500E
1500
GGT-1500E
1500
GGHT-1600E
1596
GGHT-1750E
1750
GGHT-1875E
1875
GGHT-2000E
1995
GGHT-2100E
2100
GGHT-2250E
2250
GGHT-2400E
2394
GGHT-2450E
2450
GGHT-2625E
2625
GGHT-2800E
2793
GGHT-2800AE
2800
GGHT-3000E
3000
GGHT-3150E
3150
GGHT-3200E
3192
GGHT-3375E
3375
GGHT-3500E
3500
GGHT-3600E
3591
GGHT-3750E
3750
GGHT-4000E
3990
1/2
0.84
0.52
0.41
0.031
2.50
1.12
1.25
1.66
3/4
1.17
0.73
0.57
0.044
3.50
1.84
1.75
2.33
1
1.57
0.98
0.77
0.057
4.68
2.11
2.34
3.11
1-1/4
2.19
1.37
1.07
0.082
6.54
2.94
3.27
4.35
1-1/2
2.63
1.64
1.29
0.098
7.84
3.52
3.92
5.21
2
3.55
2.23
1.74
1.320
10.60
4.77
5.30
7.05
3
5.72
3.59
2.81
2.130
17.08
7.69
8.84
11.40
Model No.
Gas
Consumption In CFH
Table 3: Gas consumption rate
hot water boilers only
Table 4: Equivalent linear length in feet of standard iron pipe fittings for natural gas
Figure 11. Typical gas supply line installation
Pipe
Size
Inches
Standard
Medium
Sweep
Long
Sweep
Gate
Globe
Angle
Return
Bend
Side
Outlet
Tee
Elbow
Valve
GAS PIPING
This section contains sizing and construction recommendations
for fuel supply piping to Caravan gas-fired modular boiler
systems. Gas-fired equipment must conform not only to codes of
local regulatory agencies, but also to additional specifications that
may be imposed by the utility or gas supplier. Therefore, the
following information should be considered only as a guideline.
Figure 11 illustrates a typical gas supply line installation. It
consists of a main between the utility’s meter box and the boiler
system, a main shut-off valve sediment trap, gas header pipe and
drip legs on individual boilers.
Individual gas lines to individual boiler modules should be
3
⁄
4
"
diameter. Size of gas main and header pipes depends on volume
of gas required and acceptable pressure drop between meter and
modules’ gas regulator valves. Minimum pressure required at each
valve is 5 inches of water column for natural gas and 11 inches for
propane gas, measured while all boilers and other gas-fired
equipment on the same meter are firing. Small variations in gas
flow can be compensated for by adjusting gas regulator valves.
However, final pressure of gas header must vary no more than
+ 0.3 in. of water column.
Summary of Contents for CARAVAN GGHT-1050E
Page 7: ...7 Figure 8 Typical layouts for gas fired systems...
Page 13: ...13 FIELD WIRING AT MODULES...
Page 14: ...14 SC 3 SYSTEM WIRING DIAGRAM...
Page 15: ...15 SC 3 LADDER WIRING DIAGRAM...
Page 16: ...16 SC 9 SPACE HEATING WIRING DIAGRAM...
Page 17: ...17 SC 9 SPACE HEATING LADDER WIRING DIAGRAM...
Page 18: ...18 SC 9 SPACE AND DOMESTIC HOT WATER WIRING DIAGRAM...
Page 19: ...19 SC 9 SPACE AND DOMESTIC HOT WATER LADDER WIRING DIAGRAM...
Page 22: ...22 NOTES...