Installing a Rack
007-4857-002
13
If your site does not have a loading dock, arrange for a forklift to unload the system from the
transportation vehicle. Ensure that two or three people are available to help unload the equipment.
Move all crates slowly and carefully.
Figure 1-3 shows the lift openings and dimensions of a tall rack shipping crate. This figure also
shows where to position the pallet jack.
Figure 1-3
Dimensions of Tall Rack Shipping Crate
Pallet jack position
Side view
52.0
(1320.8 mm)
81.5
(2070.1 mm)
42
(1066.8 mm)
End view