![Siemens XC10 Series Installation, Commissioning Maintenance Download Page 62](http://html.mh-extra.com/html/siemens/xc10-series/xc10-series_installation-commissioning-maintenance_1265620062.webp)
Commissioning
62
Building Technologies
A6V10257473_b_en_--.doc
Fire Safety & Security Products
01.2010
13
Commissioning
Before commissioning, ensure that:
- the control unit is correctly mounted on a fixed support
- all detector bases are correctly connected
- all monitored lines are correctly connected and equipped with respective EOL
- all accessory or optional parts are present
- FCP1004-E power supply setting correspond to the mains voltage
- mains voltage is available
- batteries are installed, but not connected yet
- installation of extinguishing devices (piping, cylinders, manometers, discharged
contact …) is completed
13.1 Powering
1.
switch on the mains circuit breaker
2.
connect the batteries
and, if necessary, the total loss of power cable (see 7.2)
3.
select presetting appropriate to your country need (see paragraph 12.2)
4.
set, if necessary, user functions (see paragraphs 12.3 to 12.17)
5.
calibrate monitored control outputs 4 and 5 (see paragraph 13.2)
6.
eliminate possible faults (see paragraph 14.2)
13.2 Monitored control outputs 4 and 5 calibration
1.
select operating access level 2
2.
enter the code
2 1 4 3 2 3
on the keyboard then press "Enable/Disable
actuators" (10) key within 5 seconds:
–
display shows "CAL", "Operating access" led goes out (= calibration process
start)
3.
wait until the buzzer sounds twice (=end of calibration process). Two possibilities
can arise:
calibration success:
–
"Fault" (2) and "Actuators" (20) led goes out
–
display shows "OK" for a few seconds, then goes out, "Disable" led (6)
goes out, "Operating access" led lights up again
calibration failure:
–
display shows "4E5E" or "4E.. " or " ..5E" for a few seconds then "ECAL"
–
“Fault” led (2), "Disable" led (6) and "Actuators" led (20) led remain lit up,
"Operating access" lights up again
–
check the cable connections of the output concerned (4 and/or 5)
–
re-start the procedure at point
2
At first commissioning, monitored control outputs 4 and 5 not being calibrated, will display a fault
indication:
–
"Actuators" led (20) and “Fault” led (2) flash fast
–
"Disable" led (6) lit up fix
–
Display shows "ECAL" (= Error calibration)
Calibration fails if the resistance value measured during the calibration process is equal to 0
Ω
or > 900
Ω
Calibration of monitored output 5 is not carried out if this output is programmed “Not used”