8.6
Decommissioning the machine
NOTICE
Damage as a result of an extended period out of service
If the machine is going to be out of service for longer than six months, then take the necessary
measures for preservation and storing. Otherwise damage to the machine will result.
Record the decommissioning steps. This log will be useful upon recommissioning.
8.7
Switch off the external fan
Do not immediately switch off the separately-driven (external) fan after switching off the
machine. First wait for the machine to cool down. This will prevent the accumulation of residual
heat.
8.8
Re-commissioning the machine
When you re-commission the machine, proceed as follows:
● Study the record made when the machine was decommissioned, and reverse the measures
that were taken for conservation and storage.
● Perform the measures listed in the "Commissioning" section.
See also
8.9
Switching on again after an emergency switching-off
● Check the machine before recommissioning the driven machine after an Emergency Off.
● Eliminate all the causes that have led to the emergency off
8.10
faults
8.10.1
Inspections in the event of faults
Natural disasters or unusual operating conditions, such as overloading or short circuit, are
faults that overload the machine electrically or mechanically.
Immediately perform an inspection after such faults.
Operation
8.6 Decommissioning the machine
SIMOTICS FD 1MQ1
Operating Instructions 01/2019
115
Summary of Contents for SIMOTICS FD 1MQ1
Page 2: ...28 01 2019 14 14 V11 01 ...
Page 144: ...Maintenance 9 2 Corrective Maintenance SIMOTICS FD 1MQ1 144 Operating Instructions 01 2019 ...
Page 170: ...Disposal 11 5 Disposal of components SIMOTICS FD 1MQ1 170 Operating Instructions 01 2019 ...
Page 172: ...Service and Support SIMOTICS FD 1MQ1 172 Operating Instructions 01 2019 ...
Page 176: ...Quality documents SIMOTICS FD 1MQ1 176 Operating Instructions 01 2019 ...
Page 181: ......