BA 2510
A5E38121849A/RS-AB, 10/2016
13
①
Lubrication time controller
②
Pressure generator
③
H
2
gas
④
Pressure piston
⑤
Transparent housing
⑥
Roller bearing grease
⑦
Container floor
⑧
Connection thread
Figure 6-1
Automatic regreasing device
Table 6-1
Technical data
Grease fill quantity
125 ml
Adjustable lubrication time
0 ... 12 months
Permissible ambient temperature
-20° C ... +55° C
Maximum operating pressure
3 bar
Pressure generator
Hydrogen gas generating cell
Recommended storage temperature
+20° C
Usage period
Within 2 years of filling date
Weight including grease fill
approx. 190 g
Commissioning
CAUTION
Closed lubricator bursts
Overpressure will result if the lubricator is not opened and the grease channels are contaminated. At an overpressure of
approximately 5 bar, the lubricator will burst at the preset breaking point between the housing and the funnel.
Open the lubricator before commissioning.
Press fresh grease into blocked channels with a grease gun.
Note
Fill the lubricant channels and bearing with grease before installing the lubricator.
Procedure
1.
Clean the area around the connection thread of the greasing point.
2.
Use a knife to cut off the seal at the lubricator outlet, or remove the screw plugs.