Mounting
Laying the cables and connecting the batteries
4
20 | 32
Building Technologies
A6V10393194_d_en_--
Fire Safety
2018-11-05
1. Strip the signal cables and lay these in the housing as shown above.
2. Connect the lines to the terminal block in accordance with the following wiring
diagram.
3. Strip the DC 24 V lines and lay these in the housing as shown above.
4. Connect the DC 24 V lines to the terminal block.
5. Secure the lines with cable ties (x).
'Fault' signal transfer via input/output module
The line for the 'Fault' signal transfer of the power supply is wired to an input/output
module, such as an FDCIO221, for example.
'Fault' signal transfer to a fire control panel
The line for the 'Fault' signal transfer of the power supply is wired to a fire control
panel, such as an FC120, for example.
This connection is only permitted if the housings are mounted side by side.
Otherwise, the connection must be monitored.
3.3 k
Ω
FCnet /
C-Net
FDCIO221
Input
L
INE
O
U
T
A
+
-
-
FC120
AUX. 24V
INPUT
+
-
1
FP120-Z1