80
5 Operation
5.1.6
Recommended Procedure in the Event of Irregularities on the Circuit-Breaker 3AP2 Fl
)
Note
The following table is an aid in recognition and assessment of any irregularities occuring in operation of
the circuit-breaker.
It also enables specific details to be given if Siemens service Berlin personnel have to be summoned. In
such a case, please telephone during business hours
Tel.: +91 240 2565 142
or by fax
+91 240 2554 701
WARNING
To avoid any hazard, only qualified personnel may do the work described below.
WARNING
Work may only be done on the operating mechanism when the opening and closing spring are relaxed.
WARNING
The circuit-breaker must be switched off and earthed for SF
6
filling work.
The circuit-breaker can be switched back on when filling is complete and the earthing has been
disconnected.
Release the SF
6
-pressure before working on the screw connections of the gas chamber.