PTU50-51-56 -
installation
5.1.3 Installation in nozzle
Installing the PTU50-51-56 sensor in a nozzle, make sure the sensor bottom protrudes at least 10 mm from the
bottom nozzle.
PP
PTU50-51-56 can be installed in an extension pipe to turn away the sensor from the maximum level point.
The extension pipe must be fl at and without joints (welds, etc..), also, the pipe terminal part must be cut at 45°
and with the borders without burr.
PTU50 1,5mt - PTU51 6mt
PTU56 12mt
D (mm)
L max (mm)
D (mm)
L max (mm)
100
80
125
240
125
240
125
300
150
300