Operating instruction
PROSWING(M)
39
Fig. 37
Disconnect
JUMPER
BOARD WITH PRIORITY
BOARD WITHOUT PRIORITY
Disconnect
JUMPER
Proswing control board can work in inter lock with another pro swing board. Inter lock means that it is possible to open/close
only one door at a time. To connect two boards proceed as follow (Fig. 37):
• connect “board with priority”
AUX IN 1
to “board without priority”
AUX OUT 1-A
• connect “board with priority”
COM
to “board without priority”
AUX OUT 1-B
• connect “board with priority”
AUX OUT 1-A
to “board without priority”
AUX IN 1
• connect “board with priority”
AUX OUT 1-B
to “board without priority”
COM
Use 4x0,22 shielded cable, do not connect shield.
Set priority for opening in case of simultaneous command through parameters 15 and 17:
• set parameter
15
=2 on “board with priority”;
• set parameter
17
=1on “board with priority”;
• set parameter
15
=3 on “board without priority”;
• set parameter
17
=1 on “board without priority”;
In this way in case of simultaneous command will open Master as a first door.
Inter lock wiring and use
ATTENTION:
In case of inter lock wiring between two double Proswing the wiring has to be made between the
two master boards, whereas one of the two will be considered with priority and the other with out priority to the
interlock functioning.
NPN
PNP
Disconnect jumper near AUX OUT-1 both on board with priority and board without priority (Fig. 38).
Fig. 38
B
A