When you are concreting in the plate install any necessary
cable ducts (30 mm dia. minimum) and cables in through the
base plate. Cable ducts should have sweep bends not elbow
ones.
2.3.
When concreting in the plate check that the plate is perfectly
levelled and that the measurement of 50 - 55 mm given in Fig. 2
is followed.
Max 5 mm
55-60
Q
2. MOUNTING PLATE INSTALLATION
To install the mounting plate it is necessary to:
2.1.
Have a mounting plate manufactured to the dimensions
shown in Fig. 1. The plate will require to have concrete holding
into which the foundation plate and the anchor bolts will be
walled up. It is best if the gate structure allows the plate to be
raised up from the finished level by 50 mm. This will stop water
gathering around the operator.
REV 04 - 09/2005
Plinth
Fig. 1
6
5
200
350
1
5
0
50-55
3. PINION ASSEMBLING
3.1.
Put the spline into the motor reducer shaft as in Fig. 3.
3.2.
Assemble the pinion to the motor reducer fixing it with the
provided bolt (Fig. 3).
Fig. 3
4.
FITTING OF THE UNIT
4.1.
Fix the side fixing angulars to the motor-reducer with the
provided screws (Fig. 4)
4.2.
Fix the motor-reducer to the foundation plate adjusting the
side position and its height (Fig. 4 - Fig. 5) considering the
mentioned measurements in Fig. 2.
4.3. Remove the closing loading oil cap (red) and substitute
it with that supplied apart provided with the airhole (black).