background image

Page 21

Page 21

SECTION III

TESTING

COMPLETE SYSTEM LEAK TESTS

During pressure testing for leaks, keep the
compressor suction service valve and discharge
service valve closed to prevent air and moisture
from entering the compressor. All other valves in
the system must be open.
Sufficient liquid refrigerant shall be charged into
the system to raise the pressure to 2.5 atm. and
dry nitrogen added to obtain the desired test
pressure (20.5 atm is sufficient).
Leak testing shall be performed with an electronic
leak detector, unless the use of a halide torch is
specifically authorized by the owner.
Refrigeration piping will not be acceptable unless
it is gas tight.
If any leaks are found, isolate the defective area,
discharge the gas and repair the leaks and then
repeat the test. When testing has been completed
release all pressure freely to atmosphere.

COMPLETE SYSTEM EVACUATION

The system shall be evacuated with a vacuum
pump specifically manufactured for vacuum duty,
having a capacity of pulling a vacuum of 50
microns or less.
Evacuation of the system must never be done by
the use of the refrigerant compressor. The pump
should be connected to both the low and high
side evacuation valves with vacuum hoses. The
compressor service valves should remain closed.
A high vacuum gauge capable of registering
pressure in microns should be attached to the
system pressure readings.
Never put the compressor in operation. To check
system pressure, a hand valve must be provided
between the pressure gauge and the vacuum
pump which can be closed to isolate the system
and check the pressure.
Evacuate the system to an absolute pressure not
exceeding 1,500 microns. Creak the vacuum to
excess pressure of 0,15 atm (1 psig) with the
refrigerant to be used in the system.
Repeat the evacuation process again breaking
the vacuum with refrigerant. Install a definitive
drier of the required size in the liquid, open the
compressor suction and discharge valves and
evacuate to an absolute pressure not exceeding
500 microns. Leave the vacuum pump running
for not less than two hours without interruption.
Raise the system pressure to 0,15 atm (1 psig)
with refrigerant and remove the vacuum pump.

COMPLETE SYSTEM - CHARGING

Refrigerant shall be charged directly from original
drums through a combination filter drier.
Charge the system by means of a charging fitting
in the liquid line.

Wheigh the refrigerant drum before charging so
that an accurate record can be kept of the weight
of refrigerant put in the system. It refrigerant is
added to the system through the suction side on
the compressor, charge in vapor form only. The
process used most often to determine correct
refrigerant charge is to observe the refrigerant
flow in the sight glass in the liquid line.
As steady supply of liquid is necessary for proper
functioning of expansion valves; it can be
assumed that the system has been correctly
charged when a clear flow of liquid refrigerant is
visible.
Bubbles or foam usually indicate insufficient
refrigerant, even if there could be other reason
for the bubbles or foam to appear in the sight
glass. So, the practice to relay on the sight glass
only to determine whether the systems is correctly
charged is certainly good but not fully positive.
After the final leak test, refrigerant lines exposed
high ambient conditions should be insulated to
reduce heat pick-up and prevent the formation of
flash gas in the liquid lines.
Suction line should be insulated if exposed, to
prevent condensation.

START-UP - CHECK-OUT

Compressor and condensing unit will normally
be delivered to the job with sufficient oil for
average installation.
Check compressor for proper oil level and, if
necessary, add sufficient oil to bring the level to
the center of the cranckase sight glass.
Use only refrigeration oil recommended by the
compressor manufacturer.
Remove or loosen shipping retainers under
motor-compressor. Make sure hold down nuts
on spring mounted compressor are not touching
the compressor feet.
Check electrical connections. Be sure they are
all tight. Check high and low pressure control,
water valves, pressure regulating valves, safety
controls and adjust if necessary.

OPERATION CHECK-OUT

After system has been charged and checked-out
make sure to correctly position, attached to the
unit ice spout, the require chute (not supplied).

Perform a through re-check of entire system as
per following steps.

1. Make sure to open the water supply line shut-

off valve and that water flows freely from float
valve into float reservoir and from this to the
drum basin.

Summary of Contents for MAR 108

Page 1: ...Tel 39 02 93960 1 Aut Sel Telefax 39 02 93550500 Direct Line to Service Parts Phone 39 02 93960350 Fax 39 02 93540449 Website www scotsman ice it E Mail scotsman europe scotsman it ISO 9001 Cert n 00...

Page 2: ...alve The refrigerating and electrical system must be completedbythepurchaseraspertheinstructions given in this service manual who has to provide forthecompletecondensingunit itscontrolsand refrigerant...

Page 3: ...ections 17 Water and refrigerant circuit 17 Electrical connections 18 Installation practice 19 Mar Split in multiple installation 20 Typical non code commercial installation 20 Section III TESTING Com...

Page 4: ...230 50 3 1000 6000 1 2 1 2 2 1 SS MAR 208 400 50 3 N 230 50 3 1650 8250 1 2 1 2 2 1 SS MAR 308 400 50 3 N 230 50 3 2200 9700 1 2 1 2 2 1 SS 131 131 131 223 223 850 Cooling req ts 1800 Evap T C 18 24 2...

Page 5: ...CONTROL SETTING 0 2 Bar WATER PRESSURE CONTROL SETTING 0 8 Bar MAX WATER TEMPERATURE 35 C MIN WATER TEMPERATURE 5 C MIN WATER PRESSURE 1 atm MAX WATER PRESSURE 5 atm MIN AMBIENT TEMPERATURE 5 C MAX AM...

Page 6: ...TING 0 2 Bar WATER PRESSURE CONTROL SETTING 0 8 Bar MAX WATER TEMPERATURE 35 C MIN WATER TEMPERATURE 5 C MIN WATER PRESSURE 1 atm MAX WATER PRESSURE 5 atm MIN AMBIENT TEMPERATURE 5 C MAX AMBIENT TEMPE...

Page 7: ...ROTATING SPEED 2 4 RPM thick ice CONDENSING CAPACITY 9750 Kcal hr TD 10 15 C HEAD PRESSURE SETTING 14 16 Bar on air cooled units LOW PRESSURE SETTING 1 6 Bar on air cooled units HI PRESSURE CONTROL SE...

Page 8: ...SETTING 16 18 Bar on air cooled units 16 17 Bar on water cooled unit LOW PRESSURE SETTING 1 9 Bar HI PRESSURE CONTROL SETTING 36 Bar LO PRESSURE CONTROL SETTING 0 2 Bar WATER PRESSURE CONTROL SETTING...

Page 9: ...on air cooled units 14 Bar on water cooled unit LOW PRESSURE SETTING 1 Bar on air cooled units 0 75 Bar on water cooled unit HI PRESSURE CONTROL SETTING 34 2 A C Bar 30 2 W C Bar LO PRESSURE CONTROL S...

Page 10: ...and condenser unit with their own components with their own refrigerant and water lines fittings and electric wires terminal block b the evaporator drum unit MAR Split Unit supplied by Frimont complet...

Page 11: ...and to minimize operational checks and functions however any excessinusingautomaticcontrolsandprotections may complicate the situation at the point that some of the controls be eliminated later by th...

Page 12: ...quid lines near the condensing unit Because the appearence of an installation is important the piping should be put in as neathly as possible For best sound absorb tion it is best to put in two absorb...

Page 13: ...angements are largely offset and excess melting will not occur In most situationswherewholequantityoficeproduced isbeingusedonadailybasis itisnotnecessary to provide cooling for the ice storage room b...

Page 14: ...porator water supply 13 Water drain line 14 Liquid line service valve 15 Suction line service valve REFRIGERATED ICE STORAGE ROOM Jacket system 1 Condensing unit 2 Liquid line 3 Evaporator drum unit 4...

Page 15: ...108 128 MAR 208 308 mm inch mm inch A 621 24 45 661 26 02 B 876 34 48 1296 51 03 C 520 20 38 520 20 38 D 813 32 853 33 58 E 231 9 09 440 17 32 F 3 4 GAS 28 mm G 3 8 GAS 1 2 UNIT LAYOUT AND OVERALL DI...

Page 16: ...d to mount it firmly to avoid a suddenshiftthatwouldendagertherefrigerant lines Precautions to be observed vary with the kind of situation in which the unit is to be placed The area should be well ven...

Page 17: ...irectly to float valve line fitting of 3 4 gas copper tube is not recommended for sea water supply also make sure to fit on this same a hand shut off valve close enough to MAR unit and a proper kind a...

Page 18: ...sible for serious damages to the overload switch and motor windings Make the necessary steps so that the MAR Split Unit be electrically connected to the condensing unit control box contactor as illust...

Page 19: ...7 Water supply line 8 Hand shut off valve 9 Water filter 10 Condenser water inlet 11 Condenser water outlet 12 Evaporator water supply 13 Water drain line INSTALLATION PRACTICE SPLIT UNIT ON OFFSHORE...

Page 20: ...The automatic expansion valve is the leading multipleevaporatorsystemrefrigerantcontrol as it does not regulate the low side pressure but rather control the filling of the evaporator with refrigerant...

Page 21: ...ump COMPLETE SYSTEM CHARGING Refrigerantshallbechargeddirectlyfromoriginal drums through a combination filter drier Charge the system by means of a charging fitting in the liquid line Wheigh the refri...

Page 22: ...by 18 KT1orangeLEDblinksduringthisdelay On normal operation compressor ON KT1 LEDs orange and green are steady ON together NOTE In case on any temporally Ice maker trip OFF not alarm due to NO LOW wa...

Page 23: ...1 82 14 Let the system operate for at least two hours then check one by one the operation of each individual control and protective device for proper setting 15 Eliminate any excessive vibration or n...

Page 24: ...the jacket inner surface 2 PRINCIPLES OF OPERATION HOW IT WORKS Onfreshwaterinstallationacombinationofwater pump and water distributor tube provides a constant flow of cold water to the upper side of...

Page 25: ...when passing from the liquid line to the evaporator As the pressure decreases on the low side the expansion Valve open and refrigerant escapes into the evaporator drum channel where it absorbs heat f...

Page 26: ...f 1 570 MAR 208 and 308 have a gear reducer with a ratio of 1 525 The gear reducers are greased for life therefore they do not require any mainte nance R Water pump spay bar Used only on FRESH WATER v...

Page 27: ...LIT ADJUSTMENT REMOVAL REPLACEMENT PROCEDURES 2 REMOVE AND REPLACEMENT OF EVAPORATOR DRUM REFRIGERANT SEALING DEVICES 1 Before removing the refrigerant manifold it is necessary at first to close the v...

Page 28: ...o the correspondingportofthemanifoldandtighten it with the four head necessed screw 20 Connect the refrigerant inlet line on its manifoldfittingandtightenthefittingflarenut 3 REMOVAL AND REPLACEMENT O...

Page 29: ...inlet water temperature and ambient tempera ture 8 Check drive motor operation Normal operating temperatures are about 60 C 160 C which is hot to touch Check with amperometer Amps drawn 9 CheckVbeltfo...

Page 30: ...bit float valve holding arms and remove it from holders 11 Check nozzle orifice condition In case of obstruction clean it by pin 12 Prepare a solution in a bucket by mixing for 1 2 liter of SCOTSMAN C...

Page 31: ...om 9 to 5 24 Prepare as per 12 using SCOTSMAN sanitizer rather then cleaner Possible sanitizing solution could be by mixing 1 5 cl 5 oz of sanitizer with 5 lt 1 gallon NEVER MIX CLEANING WITH SANITIZI...

Page 32: ...unit in operation for about 10 minutes 9 Disconnect again unit from power 10 Repeat again 5 to dump reservoir from chemical solution and later rinse all parts by fresh water 11 Prepare as per 6 using...

Page 33: ...ercharge of oil in system remove charge and drier Replace recharge the system Not enough refrigerant Check for refrigerant leak Lo water level Intermittent water supply Water shut off valve closed or...

Page 34: ...ainst ice formation rotating drum Lower water level to correct value Making wet ice Surrounging air temperature Correct or move unit to cooled above 40 C 100 F location Under or over charge of refrige...

Page 35: ...Split Unit WARNING Whenconductingacontinuity check of the MAR Unit 1 Disconnect the main power source 2 DO NOT use an incandescent lamp or jumper wire conduct all tests with a voltohm meter B WHITE G...

Reviews: