1
Adjustment is effected by the four stands A to a
height between 90 and 96 cm / 35,4 and 37,8 inch.
2
Bring the heat press into a horizontal position by way
of adjusting the four stands up or down.
2.1 To do so place the spirit level included in the
shipment first on the base plate as shown in
detail in figure 2 and align the heat press in a
cross direction.
2.2 Subsequently place the spirit level on the C-
profile to align the heat press in a longitudinal
direction.
3
Mount instruments box no 1 (M6x12+ washer) and
connect the pneumatic tubes. Connect the plug with
the casing by moving it onto the bushing and
simultaneously turning the nut clockwise.
4
Push the guide rail onto the C-profile mounted in the
heat press and fix all screws (M8 x16+washer).
ATTENTION: Mind the two guide rails which are
not identical for the TWIN version. There is one
guide rail for the front and one for the back side.
There is a silvery (unvarnished) strip on the right
resp left vertical interior side of the guide rail. There
is also such an identical strip on one of the two C-
profiles which are mounted in the heat press. The
guide rails must be aligned in a way that the strips of
both the guide rail and the C-profile are on the same
side.
Now first tighten the screws on the lower side and
then the screws on the sides. Make sure that the
space between the guide rail and the C-profile is as
narrow as possible (detail view 4).
5
Fix the stands (M8x20+washer).
6
Fix the stands B in a way to assure a skid proof
position.
7
Unlock the transport fixture of the trolley on the
backside of the heat press and pull it out at the front.
Check if the trolley remains in any chosen position.
If it doesn’t the position of the heat press is not
exactly horizontal and you have to repeat step 2.2.
4.1
HEAT PRESS ALIGNMENT AND FRONT PLATE MOUNTING
- 9 -