8. Commissioning
134 | 268
Original Operating Manual | Edition 1.0 (01-2020) | CrimpCenter 64 SP
8.7
STEP BY STEP
8.7.5 Insert and align the conveyor belt
8.7.8 Adjust the Working Height of the UniCrimp
8.7.9 Activate the CrimpCenter
8.7.12 Adjust the Contact Pressure of the Wire Feed
8.7.13 Adjust the Clamping Force of the Gripper
8.7.1
Introduction
This section describes the complete commissioning of the station.
This may, among other things, affect the following areas
mechanical settings at the station
mechanical alignment of the station to the CrimpCenter
load station in the EASY software (machine menu)
configure station in the EASY software (machine menu)
reference station in the EASY software (machine menu)
set up station in the EASY software (order menu)
Caution
The safety cover is opened for commissioning!
For some steps, the confirm button must be pressed!
Observe and follow the safety instructions!
The individual steps build on each other!
Notice
The correct installation and alignment of the station is required!
The correct connection of all cables is required!
For individual steps, the CrimpCenter automatically switches off the control voltage!