Troubleshooting

Problem

Possible cause

Solution

The unit does not cool or heat suffi-
ciently

Primary air volume not present or too low

Check primary air volume

Air inlet and outlet of the inner unit clogged

Remove foreign material and clean the unit

Air in the hydraulic system

Ventilation of the hydraulic system
Please inform the installer

Installed unfavourable or malfunctions at the temperature
control or sensor

Install thermostat in a different place

Clogging of the cooling/heating register

Clean the register in accordance with the
maintenance instructions

The unit is losing water

Condensate in the register

Modify the register water inlet temperature

The water circuit of the register is leaking

Please inform the installer

Register damaged
Incorrect valve or hydraulic connection

The unit is working with too much
noise

The air intake or air blow openings or the lines are clogged. Remove foreign material and clean the unit
Loose screws and fastening elements

Tighten screws

Foreign material or dirt on register surface

Remove foreign material by careful brushing
.

Primary air volume too large for selected configuration.

Check primary air volume

Summary of Contents for DISA-H Series

Page 1: ...Ferdinand Schad KG Steigstra e 25 27 D 78600 Kolbingen Telefon 49 0 74 63 980 0 Telefax 49 0 74 63 980 200 info schako de www schako de Installation Mounting and Maintenance DISA H...

Page 2: ...ormation 4 Identification of the delivered model 4 Function 4 Installation and commissioning 5 Operating conditions 5 Material reception 5 Transport lifting and handling 5 Storage 5 Installation 6 Mou...

Page 3: ...acement of defec tive materials Recycling The inspection installation hydraulic connection and commissioning of the device must be carried out by qual ified skilled personnel only in compliance with t...

Page 4: ...nsist of copper pipes 12 mm in thickness aluminium ribs diffuser system and a steel frame Grille 3 Louvre grid for supply air and return air optional Hydraulic connections 4 Upon customer request the...

Page 5: ...tion it must be stored according to the following instructions Coolant or heating fluid water or glycols ethylene or pro pylene at a concentration below 60 Water inlet temperature above the dew point...

Page 6: ...As standard the cooling circuit pipes are attached on the outside and the heating circuits at the centre of the register 4 pipe Hydraulic connections DISA H H 2 pipe Hydraulic connections DISA H HT 4...

Page 7: ...rks During in stallation the manufacturer s specifications must be observed Temperature controls The temperature controls are mounted in accordance with the selected model This is why the instructions...

Page 8: ...onnected to the hydraulic cir cuit with flexible hos es of sufficient length Hydraulic connections were tightened properly and exhib it no leaks Connecting and fastening elements have been sufficientl...

Page 9: ...and the following formula can be used to to determine the volumetric flow V l s Primary air flow Ps Pa Static pressure The K value is taken from the following table Air density 1 2 kg m3 VZU m3 h supp...

Page 10: ...r Install thermostat in a different place Clogging of the cooling heating register Clean the register in accordance with the maintenance instructions The unit is losing water Condensate in the registe...

Page 11: ...100 SAFETY OF MACHINERY Safety of Machinery Basic terms general principles of design Part 1 Basic terminology methodology DIN EN ISO 12100 SAFETY OF MACHINERY Safety of Machinery Basic terms general p...

Reviews: