19
3. PRELIMINARY OPERATION-NOT CONNECTING WITH MOTOR
● Prior to connecting power supply with inverter, check and make sure that AC power supply voltage is within input
voltage range of the inverter.
● Connect power supply to L1/R,L2/S and L3/T input terminals of the inverter.
● Operation mode control selection
The operation mode can be divided into the following categories:
□ Operation command is controlled by panel.
(2-03=d0) (Factory setting)
IM
□ Operation command is controlled by external terminals, STOP key on panel is valid.
Two line operation control, “FWD/STOP” and “REV/STOP”
(2-03=d1, 4-04=d1)
IM
DCM
MI1
REV/STOP
FWD/STOP
MI2
□ Operation command is controlled by external terminals, STOP key on panel is valid.
Two line operation control, “FWD / REV” and “OPERATION/STOP” control configuration.
(2-03=d1, 4-04=d2)
IM
DCM
MI2
RUN/STOP
REV/FWD
MI1