Intended use

The Firefighter safety switch (FSS) has been especially developed as an additional device for direct 

current (DC) photovoltaic installations. The motor driven DC disconnect switch is made to withstand a 

continuous current flow at a maximum of 25A at a string voltage of 750 VDC, or 16A at a string voltage 

of 1000 VDC.The DC disconnect switch is used to disconnect the connected strings of the installation 

in case of an emergency situation, either under load or no-load situations. Such an emergency situation 

could be in case of fire.

NOTE: The switch enclosure and/or the operating panel enclosure may not be installed in direct sunlight 

or be in direct contact with (continuous) ingress water.

Firefighter Safety Switch

The switch enclosure needs to 

be placed as close to the string 

entry of the building as possible 

and may be placed in outdoor 

situations when needed. Due 

to its enclosure, the switch is 

protected against external

influences like dust and 

moisture. The whole set-up 

is conforms to IP65. This will 

make it resistant to direct water 

jets from all directions.

Operating Panel

The firefighter must be able to safely 

disconnect the photovoltaic installation 

which is in operation and make sure 

the installation is completely switched 

off before proceeding further. To aid the 

firefighters, the operating panel must 

be used in case of emergency to switch 

off the installation. The operating panel 

therefore needs to be placed in an easy 

to access location. The operating panel 

must be visible for fire fighters so they 

can see the status and instantly act in 

case of an emergency.

Junction Box (optional)

Combining individual string 

cables into lead cables to the 

inverter. Can optionally include 

fuses, overvoltage protection 

and arc fault detection.

Inverter

String or lead cables join into the inverter 

which provides the connection to the external 

power grid.

External fire alarm (optional)

An external alarm can also be 

connected to the Operating 

Panel and thereby activate 

the disconnection of the safety 

switches.

Operation

Powering up:

When all connections are made according to the specifications in this manual, the operating panel will 

show a green LED indicating that all connected switches are in a disconnected state OFF. This indicates  

a safe situation for the firefighter. When you release the key operated push button, the system will send 

commands to turn all connected switches ON. If this is working correctly, the red (or white) LED will blink 

momentarily and burn continuously when the command is executed. The red (or white) LED indicates that 

the switches are ON and thus an unsafe situation for the fire fighters.
NOTE: The key used to turn the switches ON must be kept separate from the operating panel and only

authorised personnel are allowed to use this.

Normal operation:

Pressing the push button will instruct the switches to break the connection between solar panels and the 

inverter. Releasing the push button with the key will instruct the connected switches to make the

connection between solar panels and the inverter.

Special operation:

 

Power down:

  If there is going to be a power down situation, the operating panel will no longer provide the

  signal commands to the connected switches after approximately 10-15 seconds.
 

Connection loss:

  If one of the connected switches looses contact with the operating panel, this switch will also

  break the connection between the solar panels and the inverter.
 

Testing the system:

  It is considered mandatory to test the firefighter safety switches at least once every three

  months. This is to ensure the system is still fully functional.

Fault situation:

When the operating panel cannot determine that all switches are in the same position or if not all switches 

have changed position within 15 seconds, both the LED’s will blink and a buzzer will sound until a reset 

has been performed.
The switches need to be checked and all placed in the same position to ensure the operating panel can 

be reset. The fault mode can be reset by pressing the push button and releasing it with the key 2 times 

within 3 seconds. This will reset the electronics and start the state check of all connected switches.

Checklist Fault situation:

 •  Check Voltage at the switch; this must be 24VDC (± 5%)
 •  Check switch positions; these must ALL be ON or OFF
 •  Check wiring of all switches; these must be according to the “Wiring Schematics” on pages 26 and 27
 •  Check wiring of the Operating Panel
 •  Check Voltage and Current of the power supply: see “Technical Data” on page 7

If a fault situation keeps occurring please contact Santon for more information:

[email protected]

14

15

EN

Summary of Contents for FSS-A300-FRU

Page 1: ...ON MANUAL INSTALLATIEHANDLEIDING INSTALLATIONSHANDBUCH MANUEL D INSTALLATION MANUAL DE INSTALACI N MANUALE DI INSTALLAZIONE EN DE FR ES IT NL THE SANTON FIREFIGHTER SAFETY SWITCH FOR PHOTOVOLTAIC INST...

Page 2: ...Fachpersonal durchgef hrt werden Die gesamten Installationsarbeiten m ssen anhand der entsprechenden lokalen Vorschriften zum Zeitpunkt der Installation berpr ft werden Important safety precautions A...

Page 3: ...gli utenti Qualsiasi variazione o modifica non descritta autorizzata nel presente manuale potrebbe annulare l autorizzazione all uso dell apparecchio Santon declina qualsiasi responsabilit per danni...

Page 4: ...of strings 1 to 3 1 to 3 Protection degree level IP65 class II IP65 class II Ambient temperature range 20 C to 50 C 20 C to 50 C Weight Approx 4 kg Approx 4 kg CE certification EN 60947 part 1 3 EN 60...

Page 5: ...ti all interruttore Bedraad de zonnepaneelkabels op de schakelaar 6 Express Wire the string cables to the spring terminals Schlie en Sie die Gleichstromkabel an den Federzugklemmen an Branchez les c b...

Page 6: ...Verbinden Sie die Stromversorgung mit dem Energienetz Branchez l alimentation au r seau lectrique Conecte la fuente de alimentaci n a la red el ctrica Collegare l alimentazione alla piastra a griglia...

Page 7: ...niet succesvol waren zie dan de lijst met oplossingen op pagina 25 21 test Press the push button to test the disconnection of the system Dr cken Sie den Taster um das Abschaltung des Systems zu teste...

Page 8: ...that all connected switches are in a disconnected state OFF This indicates a safe situation for the firefighter When you release the key operated push button the system will send commands to turn all...

Page 9: ...rsorgung im Schaltergeh use die Ansteuerung Nach ca 10 sec bekommen alle angeschlossenen Schalter einen AUS Befehl Die String Verbindungen zwischen Solargenerator und Wechselrichter werden unterbroche...

Page 10: ...tous les trois mois ceci pour permettre de garantir que le syst me est op rationnel Cas d anomalie Lorsque le panneau de commande ne peut pas d terminer si tous les interrupteurs sont ou non dans la...

Page 11: ...eses como m nimo para asegurar que el sistema siga funcionando en su totalidad Situaci n de fallo Cuando el panel de mando no puede determinar si todos los interruptores est n en la misma posici n o s...

Page 12: ...almeno una volta ogni tre mesi Ci garantisce la completa funzionalit del sistema Condizio ne di guasto Se il pannello di controllo non riesce a stabilire che tutti gli interruttori si trovino nella s...

Page 13: ...elaars in de UIT stand staan Dit geeft een veilige situatie aan voor de brandweerman Wanneer u de drukknop ontgrendeld met de sleutel zal het systeem het commando naar alle aangesloten schakelaars stu...

Page 14: ...elrichter Der Wechselrichter kann im Bedarfsfall den FSS aus und einschalten Entfernen Sie die Br cke und verbinden Sie den ffner auf X1 Der potentialfreie Kontakt des Wechselrichters kann den FSS aus...

Page 15: ...info santonswitchgear com www santonswitchgear com NEN EN ISO 9001 copyrights Santon International bv Article 90A1264 00 11 2014...

Reviews: