Installation

If excess lengths of direct-buried cable are to be fed into the termination compartments 

as the unit is lowered, special attention must be paid to the cable position 

in the fuse 

termination compartments.

 Open the doors and secure them with the door holders, to 

allow the cable to be fed over the door stiles . Then, as the enclosure is being lowered into 
place, feed the cables for connection to the fuse terminals between the horizontal cable 
guides, as shown in Figure 5 and the cable-training tag affixed to the enclosure . 

NOTICE

To avoid interference with the TransFuser™ Mountings, the cables to be connected 
to the fuse terminals must be fed between the horizontal cable guides .

Special cable training is not required in the switch termination compartments .
Make sure all compartment doors open and latch closed without binding .

Figure 5.  Cables in fuse-termination compartments must be trained between horizontal cable guides as shown to prevent 

interference with operation of the TransFuser Mounting. 

TransFuser Mounting (shown in closed position) 

rotates to open position for access to isolated, 

de-energized fuse  

Ground tabs for grounding bushing well inserts

Ground bails are mounted vertically 

Cable guides are mounted horizontally, extend 

toward TransFuser Mounting

Summary of Contents for PME Pad-Mounted Gear

Page 1: ...Instruction Sheet 2 Retain this Instruction Sheet 2 Proper Application 2 General 2 Warranty 3 Safety Information Understanding Safety Alert Messages 4 Following Safety Instructions 4 Replacement Instr...

Page 2: ...nt in this publication is only intended for a specific application The application must be within the ratings furnished for the equipment Ratings for this gear are listed on the ratings label on the i...

Page 3: ...ED ONLY TO THE IMMEDIATE PURCHASER AND END USER AS DEFINED THEREIN OTHER THAN AN END USER NO REMOTE PURCHASERMAYRELYONANYAFFIRMATIONOFFACTORPROMISETHATRELATES TO THE GOODS DESCRIBED HEREIN ANY DESCRIP...

Page 4: ...TICE NOTICE identifies important procedures or requirements that can result in product or property damage if instructions are not followed Following Safety Instructions If you do not understand any po...

Page 5: ...ng carrier immediately 1 Ask for a carrier inspection 2 Note condition of shipment on all copies of the delivery receipt 3 File a claim with the carrier 4 If concealed damage is discovered Notify the...

Page 6: ...d the actuator reaches its stop Refer to Figure 2 This single motion unlatches the mechanism and recharges the latching spring for the subsequent closing operation Pull the door open and secure it wit...

Page 7: ...h the door Pull outward on the cover of the Penta Latch Mechanism to verify that the door has latched securely If it has not use a pentahead or hexhead when applicable socket wrench or tool to rotate...

Page 8: ...enclosure will be bolted directly to the mounting pad using user furnished B inch diameter anchor bolts and supplied hardware Refer to the anchor bolt detail in Figure 4 Anchor brackets and hold down...

Page 9: ...enclosure NOTICE To avoid interference with the TransFuser Mountings the cables to be connected to the fuse terminals must be fed between the horizontal cable guides Special cable training is not requ...

Page 10: ...be assembled to the unit First bolt one of the large deflectors to the bottom of a switch or fuse compart ment frame using the supplied B zn inch serrated nuts Refer to Figures 6 7 and 8 Repeat for t...

Page 11: ...led behind the two large deflectors Then bolt the small deflector into place using the supplied B zn inch serrated nuts Confirm that the complete deflector assembly installation matches Figure 7 on pa...

Page 12: ...elbows and inserts Appropriate elbowsm and inserts must be supplied and installed by the user Before installing elbows and inserts remove the shipping covers from bushings and bushing wells Ground eac...

Page 13: ...tral ground wires to the ground bails and rods provided making sure that cables have sufficient mobility to allow the elbows to be moved from bushings to parking stands Connect the ground pads inside...

Page 14: ...nd replace the bolts to plug the blind tapped holes 1 Check the interior of the pad mounted gear Remove all foreign materials and tools 2 that may have been mislaid and sweep the interior clear of deb...

Page 15: ...onducted at no more than 0 75 times the values shown When making ac tests the time duration for application of the test voltage should be limited to less than 10 seconds 3 The column headed Dc is give...

Page 16: ...Stainless Steel Enclosure1 With Olive Green Outdoor Ultradur Finish A10 With Light Gray Outdoor Ultradur Finish A12 Hexhead Actuator for use in lieu of pentahead actuator on all Penta Latch Mechanism...

Reviews: