background image

S&C Instruction Sheet 761-505   

7

Shipping and Handling

Inspection

Examine the shipment for external evidence of damage as 
soon after receipt as possible, preferably before removal 
from the carrier’s conveyance. Check the bill of lading to 
make sure the listed shipping skids, crates, and containers 
are present:

If there is visible loss and/or damage:

1.  Notify the delivering carrier immediately.
2.  Ask for a carrier inspection.
3.  Note condition of shipment on all copies of the delivery 

receipt.

4.  File a claim with the carrier.

If concealed damage is discovered:

1.  Notify the delivering carrier within 15 days of receipt of 

shipment.

2.  Ask for a carrier inspection.
3.  File a claim with the carrier.

Also notify S&C Electric Company in all instances of 

loss and/or damage.

Packing

Study the erection drawing carefully and check the bill of 
materials to be sure all parts are at hand. When a standard 
mounting arrangement is specifi ed, the shipment includes:
•  Three switch poles
•  Operating-pipe sections for interphase, horizontal-

connecting, and vertical sections (The switch may be 
furnished “less operating pipe,” if specifi ed.)

•  Operating-mechanism components, such as handle, 

guide bearings, outboard bearing, and couplings—
each tagged and keyed to the bill of material for ready 
identifi cation
The components included with these modifications are 

shown on the erection drawing bill of material under the 
specified “-SX” suffix. They include:

-S1  One tubular fiberglass insulating section in vertical 

operating shaft

-S2  One Cypoxy™ Insulator unit in vertical operating 

shaft

-S3  Insulated interphase sections and one tubular 

fiberglass insulating section in the vertical operat-
ing shaft

-S4   Insulated interphase sections and one Cypoxy 

Insulator unit in the vertical operating shaft

-S6  Key interlock—single lock for a “locked-open” 

application

-S6L  Provision for key interlock—allows future addition 

of single lock for “locked-open” application

-S7  Auxiliary contact switch with 4 N/O and 4 N/C 

contacts (600 Vac, 20 A)

-S8  Provision for power operation of pole-mounted 

switches by S&C Switch Operator—Type AS-10

-S9  Provision for power operation of steel-structure or 

pedestal-mounted switches by S&C Switch Opera-
tor—Type AS-10

-S16  Provision for power operation by S&C 6801M Auto-

matic Switch Operator

“-V1,” “-V2,” or “-V3” adds (one, two, or three respec-

tively) extra 6-foot-10-inch (208-cm) lengths of pipe and 
includes the appropriate number of extra couplings and 
guides.

Reference drawing RD-10006, detailing the various modi-

fications, is included in addition to the erection drawing.

Power Operation: 

If suffi x “-S8” or “-S9” is specifi ed, 

S&C Instruction Sheets 769-510 and 769-511, “S&C Switch 
Operators—Type AS-10,” are included with the switch 
operator shipment. Instruction Sheets 769-510 and 769-
511 cover installation, operation, and adjustment of 
the appropriate switch operator and should be used in 
conjunction with this instruction sheet where applicable. 
If suffi x “-S16” is specifi ed, associated S&C Instruction 
Sheets for the 6801M Automatic Switch Operator are 
included with the switch operator shipment. Not all 
mounting arrangements are suitable for power operation; 
consult the nearest S&C Sales Offi ce for details.

Fused Interrupter Switches:

 The installation procedure 

described in this document is also applicable to three-pole 
double-break style Alduti-Rupter Switches with Power 
Fuses.

Summary of Contents for Alduti-Rupter

Page 1: ...s 2 Read this Instruction Sheet 2 Retain this Instruction Sheet 2 Proper Application 2 Warranty 3 Warranty Qualifications 3 Safety Information Understanding Safety Alert Messages 4 Following Safety In...

Page 2: ...or such qualified persons They are not intended to be a substitute for adequate training and experience in safety procedures for this type of equipment Read this Instruction Sheet NOTICE Thoroughly an...

Page 3: ...are those stated in Price Sheet 150 or Price Sheet 153 and THERE ARE NO EXPRESS OR IMPLIED WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE ANY EXPRESS WARRANTY OR OTHER OBLIGATION PR...

Page 4: ...ecautions are not followed NOTICE NOTICE identifies important procedures or requirements that can result in product or property damage if instructions are not followed Following Safety Instructions If...

Page 5: ...age Description Part Number A DANGER Electrocution Hazard G 6580 1 B WARNING Piercing Set Screws G 3176R1 C WARNING Handle Operation G 4400R5 D WARNING Electrocution Hazard Grounding Strap G 6596 This...

Page 6: ...lothing in accordance with safe operating procedures and rules 4 SAFETY LABELS AND TAGS Do not remove or obscure any of the DANGER WARNING CAUTION or NOTICE labels Remove tags ONLY if instructed to do...

Page 7: ...sections and one tubular fiberglass insulating section in the vertical operat ing shaft S4 Insulated interphase sections and one Cypoxy Insulator unit in the vertical operating shaft S6 Key interlock...

Page 8: ...lly Closed position during installation of the interphase and vertical operating pipe sections S C recommends tying the switch blades to their jaw contacts with wire or a cable tie WARNING DO NOT lift...

Page 9: ...tch poles and bell crank base s or bracket s from their crates and arrange them on the ground in the same order in which they will be mounted on the pole or structure Protect the bearings from contami...

Page 10: ...g on the live parts Avoid allowing the switch poles to swing while lifting Lifting the switch by the live parts will damage the switch Rough handling may cause damage to the blades and contacts Failur...

Page 11: ...ndue strain on the insulators and throwing the blades out of alignment resulting in difficulties operating the switch Use shims as required STEP 6 Lift or hoist the bell crank assembly including baseo...

Page 12: ...ert the operating pipe section into the coupling and finger tighten the clamp bolt s 3 Adjust the operating pipe to the correct length Then tighten the clamp bolt s to final tightness 4 Tighten the pi...

Page 13: ...nk is mounted outboard of the switch poles Install the pipe section connecting the driven arm of the bell crank to the nearest switch pole See Figure 12 If two bell cranks are used in a double offset...

Page 14: ...ipe sections furnished is threaded at one end to accommodate the operating handle assembly See Figure 13 Install this section of pipe last with the threads at the lower end If only one vertical operat...

Page 15: ...guide arm pointing upward at a 45 degree angle See Figure 15 A positioning stud is furnished that holds the rod guide at 45 degrees Follow the directions in Installing Pipe Couplings with Piercing Set...

Page 16: ...es an S C Type AS 10 Switch Opera tor as signified by the addition of the standard minor modifica tion suffix S8 or S9 to the erection drawing number for 34 5 kV and 46 kV switches refer instead to S...

Page 17: ...TEP 17 Fasten the free end of the grounding strap to the lowest vertical operating pipe section a few inches above the operating handle assembly with the U bolt connector provided for this purpose See...

Page 18: ...shipping CAUTION The switch should be opened and closed slowly only when checking for alignment and complete closure When opening or closing the switch in service do not slow down or stop part way Ar...

Page 19: ...oosen the clamp bolt on the low est rod guide or bell crank coupling and move the handle to a position less than 20 degrees from the Closed position Then torque the clamp bolt on the lowest rod guide...

Page 20: ...n the locking disc on the operat ing handle See Figure 23 STEP 22 Block one of the two slots in the locking disc with the blocking screw provided The slot to be blocked depends on whether a locked ope...

Page 21: ...sm should lie against its closed stop See Figure 26 c If none of the switch poles are fully closed the effective length of the vertical operating pipe may need to be increased Loosen the vertical oper...

Page 22: ...poles are fully closed readjust the take up screw s on the adjustable pipe coupling s at the switch pole to increase or decrease the effective length s of the interphase operating pipe s See Figure 2...

Page 23: ...Shorten ing the adjustable lever arm increases switch blade travel Then readjust for full operating handle travel as described on page 18 f Repeat this procedure shortening the adjustableleverarmofthe...

Page 24: ...igure 31 NOTICE After readjusting be sure to retighten the locknut on each adjustable pipe coupling take up screw the clamp bolt and piercing set screw on the pipe coupling at the rod guide or bell cr...

Page 25: ...assembly in the fully Closed position verify the minimum clearance between each blade shunt contact and its respective interrupter housing See Figure 33 The shunt contacts may be bent as required to...

Page 26: ...ve engagement with their respective interrupter opening levers as shown in Figure 35 Simultaneity is essential to ensure both interrupters share the interrupting duty The opening lever on one or both...

Page 27: ...tings to the stationary insulators See Figure 37 Shift the terminal base castings as required Tighten the terminal base casting cap screws and recheck for conformance to the conditions outlined above...

Page 28: ...aluminum alloy body connectors the following procedures should be used a Thoroughly wire brush the current transfer surfaces of each connector and immediately apply a liberal coating of Penetrox A av...

Page 29: ...king fault currents STEP 26 Remove the padlock from the locking bar on the operating handle assembly Withdraw the locking bar See Figure 39 a If the operating handle assembly is furnished withakeyinte...

Reviews: