S&C Instruction Sheet 1045M-510
9
Before Switch Operator Installation
STEP 4.
If necessary, install the batteries. If the batteries were not installed at the
factory, use the insulated jumper and hardware provided to install them now.
Make sure the battery connections are tight and the battery hold-down clamp is
securely fastened.
(a) Open the faceplate and make sure the 24-volt circuit breaker (near the center of
the enclosure) is in the Off setting.
(b) Find the studs on the back and floor of the enclosure (left side for the rotating
unit, right side for the reciprocating unit).
(c) Attach the black insulated terminal lead connected to the shunt to the (–)
negative terminal on one battery.
(d) Attach the red insulated terminal lead connected to the dc breaker to the (+)
positive terminal on the other battery.
(e) Slide the batteries in place, with the connections toward the back of the
enclosure.
(f) Align the holes in the battery hold-down clamp with the studs. Place the clamp
on the batteries, and use retaining nuts to secure it. See Figure 1 on page 8.
(g) Use the insulated jumper to connect the remaining (–) negative terminal (black)
on one battery to the remaining (+) positive terminal (red) on the other.
Figure 2. The 6801M Switch Operator faceplate (shown for the 6801M Switch Operator with the
IntelliTeam SG software option).