Start-up
When using reverse installation (with the de-
vice mounted above the measuring point),
the differential pressure lines may partly get
drained when depressurizing the system.
When starting up the system again, vent the
measurement setup to allow it to fill with con
-
densate.
Measurement of liquids
1.
Slowly
open
the high-pressure line.
2.
Close
the equalizing valve or bypass of
the valve block.
3.
Open
the low-pressure line.
4.
Undo the vent screw on the dp cell until
all the air has escaped. Retighten the
screw.
5.
Check zero (see section 8.3), and put the
device back into operation.
7.3 Water drainage
When measuring gas, drain condensed wa-
ter from the separation chambers from time
to time.
Close valves in the differential pressure lines
(valve block) before opening the drain plugs.
NOTICE
!
NOTICE
!
Summary of Contents for Media 6 Z
Page 38: ...38 EB 9527 3 EN ...
Page 39: ...EB 9527 3 EN 39 ...
Page 40: ...40 EB 9527 3 EN ...
Page 41: ...EB 9527 3 EN 41 ...
Page 42: ...42 EB 9527 3 EN ...
Page 43: ...EB 9527 3 EN 43 ...
Page 46: ......