6-2
EB 8075 EN
Start-up
Before start-up or putting the valve back into
service, make sure the following conditions
are met:
− The valve is properly installed into the
pipeline (see the 'Installation' section).
− The leak and function tests have been
completed successfully (see the 'Testing
the installed valve' section).
− The prevailing conditions in the plant
section concerned meet the valve sizing
requirements (see information under
'Intended use' in the 'Safety instructions
and measures' section).
Start-up/putting the valve back into opera-
tion
1. Allow the valve to cool down or warm up
to reach ambient temperature before
start-up when the ambient temperature
and process medium temperature differ
greatly or the medium properties require
such a measure.
2.
Slowly open the shut-off valves in the
pipeline. Slowly opening these valves
prevents a sudden surge in pressure and
high flow velocities which can damage
the valve.
3. Check the valve to ensure it functions
properly.
Summary of Contents for EB 8075 EN
Page 28: ...3 14 EB 8075 EN...
Page 34: ...4 6 EB 8075 EN Shipment and on site transport...
Page 58: ...8 4 EB 8075 EN...
Page 60: ...9 2 EB 8075 EN...
Page 66: ...12 2 EB 8075 EN...
Page 68: ...13 2 EB 8075 EN...
Page 70: ...14 2 EB 8075 EN...
Page 77: ......
Page 78: ......
Page 79: ......