Doc.-ID: 180731-PT08BAU-SS-Ex Installation Manual rev.00.docx, Page 18 of 24
Attention!
Make sure that the O-ring seal of the housing is perfectly placed in its
groove, not damaged and not contaminated.
Attention!
If the thread surface is damaged, the housing must not be longer
used!
Attention!
Ensure that no foreign objects get entrapped in the housing.
The countersunk screw with internal hexagon (DIN 7991) on the flange
component must absolutely be re-tightened (approximately 2.5 Nm
tightening torque is required).
6.3
Electrical connection and commissioning
Attention!
The electrical connection of the equipment must only be carried out
by officially qualified and skilled personnel!
Attention!
It is absolutely necessary to ground the ExCam
®
series housing via the PA
connection (4mm solid/rigid conductor)
Attention!
As far as possible, the first commissioning of the device should be
carried out at positive temperatures, in order to prevent condensation
in the housing.
Prior to commissioning, all tests must be carried out, as indicated by the national regula-
tions. Furthermore, the correct function and installation of the device must be checked in
accordance with this user manual and other applicable regulations.
Incorrect installation and operation of the camera may lead to a loss of warranty!
The functio
nal “Commissioning” of each device is described in the respective user
manual.
Summary of Contents for ExCam Series
Page 1: ...ExCam Series T08 Installation Manual 2018...
Page 22: ...Doc ID 180731 PT08BAU SS Ex Installation Manual rev 00 docx Page 22 of 24...
Page 23: ...Doc ID 180731 PT08BAU SS Ex Installation Manual rev 00 docx Page 23 of 24...
Page 24: ...Doc ID 180731 PT08BAU SS Ex Installation Manual rev 00 docx Page 24 of 24...