EN |
17
RIS PE 3.0 v2020.1
7.5. SYSTEM ADJUSTMENT GUIDELINES
Before commissioning, device launching and adjustment works must be done only by qualified and trained personnel. Automatic control system of
the ventilation unit must be properly adjusted to work adequately. Also, install measuring and operating devices in line with the provided guidelines.
Air temperature sensors and air quality converters.
Supply air temperature sensors and air quality converters (if additionally used) must be
mounted as far as possible from the ventilation devices (within the confines of sensor cable) up to the first branch or turn of the air transportation
system. This requirement is necessary to ensure the accuracy of measurement.
7.6. CONTROL BOARD RG1
Summary of Contents for RIS 400 PE 0
Page 1: ...RIS PE 3 0 EN MOUNTING AND INSTALLATION INSTRUCTION...
Page 30: ...30 RIS PE 3 0 v2020 1...
Page 31: ...31 RIS PE 3 0 v2020 1...