3.6. TEMPERING / HEAT-STRENGTHENING

• 

Drying:

•  Use an air-blowing installation equipped with filters
•  Clean and regularly maintained filters;

• 

Water should be sprayed directly onto the glass, not onto the brushes (as per below drawing;

• 

The glass sheet does not stop inside the washing machine. The washed panes should not remain in 
the washing unit for any length of time, especially not while the brushes are rotating;

• 

No water must remain on the coated surface after the drying process;

It is strongly recommended that the washing machine is regularly cleaned, especially for the brushes 
and in areas where demineralised water is used. Clean the filters every day, and the tanks every week. 
For the brushes, steam cleaning gives good results, but do not spray the bristles with high temperature 
and high pressure water.
• 

In case dirt / stains are still present on the coating after the washer, cleaning may be performed 
using a soft cloth and isopropanol (IPA) or ethanol followed by rapid drying, provided this is done 
carefully and immediately after contamination has occurred.

• 

For interim stacking of washed panes, use cork pads near the edge of the sheets.

• 

In case, in a further step, for VISION-LITE® or VISION-LITE® II, it is of the highest importance that no 
residues or marks are left on the coating surface after the exit of the pre-processing washing machine.

For instance, pollutions left on the coating may induce at tempering hot corrosion (giving the aspect of 
pinholes) of the coating. Such marks may not be washable. Also, even in case of annealed version, there 
is a risk that residues will be not eliminated during final washing.

VISION-LITE® II (and only the ‘to be tempered’ version) can be heat-treated to get a tempered / heat-
strengthened coated glass.

The cleanliness of VISION-LITE® II coating before entering the tempering furnace is important.

 From 

the exit of the washer to the entrance of the tempering furnace, only the use of perfectly clean gloves 
should be permitted. The coating may be gently cleaned with isopropanol (IPA) on the furnace entry 
bed to remove dirt or marks (from gloves, separators, fingerprints…).
Special care and attention must be taken at every stage of processing, in particular before and during 
the toughening process. Please consult your local TSM if necessary. Washed panes should be toughened 
maximum 2 days after washing.

Generally speaking, VISION-LITE® II can be toughened using oven settings that are suitablefor standard 
clear glass. The exact settings being of course furnace dependent cannot be given in these guidelines. 
However, it is recommended that the sheets should be handled as “cold” as possible to achieve a flawless 
coating after toughening and obtain the desired level of stress (breaking pattern). This means that the 
temperatures and heating times are set so as just to avoid breakage in the blower box and to meet the 
requirements for single-sheet safety glass.

3.6.1. General

3.6.2. Prerequisites for tempering / heat-strengthening

3.6.3. Toughening instructions

Summary of Contents for VISION-LITE

Page 1: ...VISION LITE VISION LITE II PROCESSING GUIDELINES MAY 2022 1 PROCESSING GUIDELINES VISION LITE VISION LITE II...

Page 2: ...VISION LITE VISION LITE II PROCESSING GUIDELINES MAY 2022 2 DOCUMENT CODE DATE SGG QD C GUI 0013 B 05 2022...

Page 3: ...he coating 7 1 5 2 Identification of the coated face 9 2 Transport acceptance storage and handling 9 2 1 Transport 9 2 2 Receipt of the delivery 10 2 3 Storage 11 2 3 1 General 11 2 3 2 Shelf life 11...

Page 4: ...of Insulating Glass Units 17 3 13 Processing quality checks 18 4 Environment waste glass health issues 19 5 Glazing instructions 19 6 Protection cleaning and maintenance of the end products 20 6 1 Pr...

Page 5: ...can be used in single or double glazing unit VISION LITE is mainly used in retail shops and museums as display case glazing and in exteriors as shop windows or balustrades VISION LITE can also be use...

Page 6: ...from this norm Uniformity defect slight visible variation in colour in reflection or in transmission within a coated glass pane or from pane to pane Stain defect in the coating larger than punctual de...

Page 7: ...effect it must be also present on face 2 of the pane This coated glass can be laminated taking care to always place the coating outside of the laminate Use of the coating against the PVB is not allow...

Page 8: ...panel can be replaced with a low emissivity coated glass like PLANITHERM XN or ECLAZ for instance The association of Semi VISION LITE with other low emissivity coatings must be assessed case by case p...

Page 9: ...ransported in 2 8 tonnes packs jumbo or split sizes Glass sheets must be transported vertically The individual sheets are packed with the coated side towards the inside of the frame unless otherwise r...

Page 10: ...ed on the identification label All deliveries are identified with a label providing the following data 2 2 RECEIPT OF THE DELIVERY No claim can be accepted for damages caused during and after processi...

Page 11: ...ns with vacuum cups on the coated side cannot be avoided make sure that the vacuum cups are perfectly clean Not all solutions are suitable for cleaning vacuum cups see manufacturer documentation for d...

Page 12: ...other ordinary coated glass However the following recommendations have to be respected Any irregularity or damage of the edges must be avoided since it is likely to increase the risk of breakage durin...

Page 13: ...h 3210 6000 mm PLF the usable surface is 3170 5960 mm VISION LITE range does not need to be edge deleted whatever the configuration of use It could be used with polysulphide polyurethane or silicone I...

Page 14: ...and 8 Brushes Flexible soft clean polyamide bristles Maximum diameter of 0 2 mm 20 40 mm long Make care that all the brushes are perfectly clean and regularly maintained Any hard brushes must be lift...

Page 15: ...utions left on the coating may induce at tempering hot corrosion giving the aspect of pinholes of the coating Such marks may not be washable Also even in case of annealed version there is a risk that...

Page 16: ...lass presence this must be in certain situations used manually in fact the very low reflectance of the VISION LITE II glass may not be detected by the sensor and therefore it may not send the informat...

Page 17: ...LITE II is assembled into double glazed units this should be performed within 2 days SEMI VISION LITE for annealed laminated glass or tempered SEMI VISION LITE II only can be laminated with the coatin...

Page 18: ...etc Visual detection of roller wave Normal control of the toughening quality break pattern etc After heat soak testing Visual aspect control scratches oxidation corrosion splinters etc Check that no d...

Page 19: ...paint plaster mortar it is recommended that glazings are installed after all other work on site has been completed In case this cannot be respected efficient protection of the glazing by means of poly...

Page 20: ...cleaning the coating are isopropanol IPA or ethanol Cleaning with the help of solvents must be immediately followed by normal washing with water and rinsing The owner of the building must ensure the...

Page 21: ...ITE VISION LITE II PROCESSING GUIDELINES MAY 2022 21 SAINT GOBAIN INNOVATIVE MATERIALS POLSKA SP Z O O ODDZIA GLASS ul Szklanych Dom w 1 42 530 D browa G rnicza www saint gobain glass pl bgp saint gob...

Reviews: