6.
Installing the Power Door Control Module
(Reference wiring diagram on page 9)
a) Connect the wires as shown in the diagram. Use the appropriate fuses as noted.
b) Install the power door control module to the left side near the pennant plate.
7. Install the Operator and Door Curtain
a)
Place the operator shaft into the U-Brackets on the pennant plates. The tension pin and label shall
be on the right while looking into the compartment as shown in Fig. 7.
b)
The straps should wrap around the operator diameter approximately 1-1/4 times, then drape
down approximately 5”.
c)
Attach the 1/4-20 bolts and nuts to the shaft and U-Brackets.
d)
Feed the top slat of the shutter on top of the sprockets. It will be necessary to drive the motor and
gearbox manually in order to feed the curtain into the compartment. Let the curtain hang behind
the operator. With the curtain in this position place the T-clip into the slots on the top slates and
secure. Do not force, lift or lower the curtain quickly or slam it against the stops at the top or bottom.
Damage to the motor gear train will result if the gear motor is not allowed time to rotate. It is
possible to attach a temporary 12 VDC power to the motor’s red and black wires to drive the motor
around to install the curtain. You will have to remove the gray and brown wires previously installed
to do this.
e)
After the curtain is installed, slightly rotate the operator clockwise and remove the tension pin (nail).
Reverse the rotation and slowly roll shutter around operator, so the bumpers on the bottom rail
touch the header.