Rugged Interactive
Unit 1, Callywith Court,
Callywith Industrial Estate,
Bodmin, Cornwall, UK
PL31 2RQ
+
44 (0) 1726 981 123
www.rugged
-
interactive.co.uk
hello@rugged
-
interactive.co.uk
SkyClimb -
Installation Checklist
©
Rugged Interactive
2021
SkyClimb Installation Checklist
Please complete this checklist after any installation:
Check 1: Pre-power up checks.
Mounted onto a wall of a construction capable of supporting its gameplay.
☐
All fixings are tight and secure.
☐
No signs of damage, component failure and/or missing parts.
☐
No trapped and/or pinched cables.
☐
No loose cables that could become a tripping hazard.
☐
All long cables are supported at least every 50 cm.
☐
Adequate strain relief provided for connection points.
☐
Kept out of direct sunlight during the day.
☐
All electric components away from contact with water.
☐
Protective plastic sheet from each pod removed.
☐
Check 2: Power up.
All pods light up.
☐
Text appears on the hub display and is as expected.
E.g. SkyClimb.
☐
Sound volume is at a suitable level
*
.
☐
Large display screen is displaying graphics. (
if included
)
☐
Touchscreen operational and responsive. (
if included
)
☐
Check 3: Select ClearOut (Speed) via Quick Start.
Program counts down from 3 and begins.
☐
All pods active and operational.
☐
Check all pods for colours: red, green, blue.
☐
Sounds can be heard when the lights are hit.
☐
Program plays as described in the Programs Guide.
☐