5. Securing walls to floor
Fit the kick strip centrally to the bottom of the door opening using 4 x 40mm nails. Ensure the panels are sitting square on the floor. Secure them by screwing through the
panel frames into the floor using 8 x 60mm screws.
Panel frame
Back panel
Side panel
60mm
50mm
50mm
It is recommended to drill pilot
holes for these screws with a 2mm
drill bit before assembly.
50mm
60mm
Back apex panel
Front apex panel
4. Apex panels
Place an apex panel on top of the back wall, make sure the bottom shiplap board of the apex panel fits correctly into the shiplap board of the back wall. Secure using 2 x 50mm
screws, screw up through the top frame of the back wall into the bottom frame of the apex panel. Fit the front apex in the same way using 2 x 60mm screws. Attach to the
front apex the door frame beading using 3 x 25mm nails. Secure it to the bottom of the framing, up against the cladding 560mm from the left-hand front panel as shown below.
Shiplap cladding
Apex frame
560mm
Door frame bead-
ing
25mm
40mm
Drill
6. Roof purlins
Insert the four roof purlin into the rebates in the apex sections. Fix in place at the ends of the purlin, using 2 x 50mm screws per purlin. Screw through the purlin and into
the frame of the apex panels.
60mm
60mm
25mm
25mm
19mm
7. Hanging the doors
Fit three hinges to the long rebated edge of each door. Position them 150mm from the ends and one centrally between the other two. Attach each hinge using 2 x 25mm
screws per hinge. Open the hinges and fit them around the door frame, adjust the door to the correct height and fix the hinges to the door frame using 3 x 25mm screws
per hinge. Attach the tower bolts to the inside of the left door as shown using 4 x 19mm round head screws per bolt.