22
Rockwell Automation Publication 1512A-UM101B-EN-P - December 2021
Chapter 2 Installation – Standard Enclosure
9. Remove the retaining 1/4-20 self-tapping screws from removable bus
access barriers to expose incoming cable connections to main bus (see
10. Install incoming line cables to power bus, torque to specifications (see
Recommended Torque Values on page 10
).
11. Reverse procedure after cables have been installed.
Front Access – Bottom Incoming Line Cables
If the incoming line cables in your cabinet enter the section from the bottom,
follow the same procedure as for
Front Access – Top Incoming Line Cables and
.
1. Open the power cell door.
2. Locate incoming cable duct at rear left-hand side of power cell (see
).
3. Remove the 1/4-20 self-tapping screws from the cable duct access
barriers. Remove barriers.
4. Route and install incoming line cables to power bus. Torque to
specifications (see
Recommended Torque Values on page 10
5. Reverse procedure after cables have been installed.
Figure 14 - Access to Bottom Incoming Line Cables
Access to incoming cable duct in the power cell is also required.
ATTENTION:
Ensure all barriers are replaced before re-energizing
the equipment. Failure to do so may result in electrical faults and can
cause damage to equipment or severe injury to personnel.
Cable duct
access barrier
Bottom incoming
cable duct in
power cell