7.3. Before the heating season launch, it is also recommended to test the heating system with one and a half 

working pressure. 

7.4. In the forced heating system, the natural circulation of water is first checked, that is, by launching the 

boiler  into  operation,  the  pump  is  not  turned  on,  and  the  system  is  checked  for  the  possibility  of  working 
without a pump. 

7.5. A safety valve (with a diameter corresponding to the boiler power) is installed on the nozzles which are 

directly  connected  to  the  boiler  (supply  nozzle)  or  pipeline  without  intermediate  shut-off  systems  in 
accordance with the “Rules for arrangement and safe operation of steam boilers with a steam pressure of no 
more than 3 kgf/cm

2

, water boilers and water heaters with the water heating temperature not higher than 85°C” 

and instructions from the manufacturing plant attached to safety valves. 

7.6. 

IT  IS  FORBIDDEN

  to  alter  the  design,  decorative  casing  and  insulation  of  the  boiler,  the 

dimensions and threads of the connecting pipes, to change boiler’s functions or operate it in a faulty 
condition. 

7.7. 

IT IS FORBIDDEN

 to break sintered coal and rock found on the grates through the  charging 

port  due  to  possible  damage  to  the  grates.  Sintered  coal  can  be  torn  by  a  metal  rod  through  the 
charging port. The accumulated rock is removed only through the ashpit by an emergency shutdown 

of the boiler, by cleaning without shutting down or at the end of the heating season. 

 

8. Safety rules for installation, maintenance and operation of the boiler 

8.1. It is prohibited to operate the boilers in violation of installation, maintenance and operation procedures. 

8.2. Only adult personnel who are familiar with the general safety regulations of the company operating the 

boiler and the safety rules for the installation and maintenance of “” boilers are allowed to maintain the boiler. 
In addition, the staff must have experience and understanding of the operation of heating boilers and systems, 
be aware of these instructions, as well as  must know and put into practice the ways to eliminate all possible 
emergencies. 

8.3. The boiler is fireproof. The temperature of its outer surfaces does not exceed the normalized values, 

but  during  its  operation,  the  gas  flue  pipes  and  chimney  are  heated  to  a  high  temperature.  In  order  to  avoid 
burns,  the  heating  parts  of  the  boiler  must  be  insulated,  and  the  maintenance  personnel  must  work  in  a  suit 
made of thick fabric and gloves. 

8.4. In order to avoid fire and burns during an emergency shutdown of the boiler, the boiler plant must be 

equipped with fire extinguishing agents (sand, water, fire extinguishers, etc.), and the staff must have shoes on 
a solid sole with a closed top. 

8.5.  In  order  to  avoid  a  face  burn,  it  is  prohibited  to  remove  the  boiler  lid  when  inspecting  the  boiler  or 

loading fuel into the bunker with the ashpit door open. 

8.6. Do not use flammable liquids for  the boiler ignition and during its operation. It is not allowed to fill 

them through the loading door or in any other way in order to increase the boiler’s nominal power. 

8.7. It is prohibited to store fuel behind the boiler (ashpit) or near the boiler at a distance of less than 10 m. 

It is prohibited to place objects and flammable liquids on the boiler, as well as at a dangerous distance from 
the boiler (less than 10 m). 

8.8.  When  transporting  the  boiler,  loading  and  unloading  work,  follow  the  general  rules  of  accident 

prevention appropriate for this type of work. 

8.9. When installing the boiler follow the general rules of  accident prevention when installing equipment. 

In order to avoid deformation or depressurization of the boiler and its parts, it is prohibited to drop or throw 
them from a height of more than 0.1 m. 

8.10. In order to avoid injuries in case of falling of the installation and operating personnel, it is forbidden 

to work from random objects and loose scaffolds and stairs. When non-factory-made scaffold is used as a site 
for maintaining the boiler, it should be fenced. 

8.11. Operating and installation personnel must have safety helmets and gloves. 

8.12.  In  a  prominent  place  in  the  boiler  plant  there  should  be  an  instruction  developed  by  the  company 

operating the boilers, obliging the fireman to observe safety precautions, as well as defining the procedure and 
actions of the fireman during emergency situations in the heating system of the enterprise. 

Summary of Contents for UNIVERSAL RG Series

Page 1: ...assport data and the boiler you have purchased which do not affect its technical characteristics and consumer properties When purchasing a boiler check the completeness appearance of the product and t...

Page 2: ...ek ee The warranty period of the boiler manufactured in accordance with EN 303 5 2012 GOST 20548 TC 4931 007 82749029 2007 is 24 months from the date of sale via a retail network The warranty period f...

Page 3: ...E 8 6 4 HEATING SYSTEM INSTALLATION 8 6 5 THE BOILER IGNITION PROCEDURE 8 6 6 BOILER SHUTDOWN PROCEDURE 9 6 7 BOILER OPERATION 9 7 SYSTEM TESTING SAFETY DEVICES 10 8 SAFETY RULES FOR INSTALLATION MAIN...

Page 4: ...etc 1 7 As a rule the boiler is installed directly in the vicinity of the heated facility or directly on the facility when a height of the boiler plant is at least 2 8 m When installing the boiler ou...

Page 5: ...layer which virtually eliminates the formation of carbon monoxide and provides the boiler with efficiency of up to 84 when operating in optimal mode 4 6 The average seasonal fuel consumption calorific...

Page 6: ...ried out on the operating boiler by shaking grates 20 fixed on rotating shafts using two arms 17 located on the front part of the ashpit Ash and unburned particles of coal pour down into the ashpit 20...

Page 7: ...several boilers are installed inside one boiler plant the boilers are connected to the heating system through a supply and return manifold mounted between the boilers and the wall of the boiler plant...

Page 8: ...recommended to fill the system with soft water that does not contain salts and other impurities which being deposited on the walls of pipes and jacket of the boiler impair heat transfer and their effi...

Page 9: ...uid or circulation along a small or one of the heating system circuits due to its unregulated or obstructed pipes etc 6 6 3 Emergency shutdown of the boiler is performed as follows Tightly close the a...

Page 10: ...ashpit junction with the heat exchanger are carefully sealed with fireproof gaskets and cords 6 7 10 The boiler s construction allows its cleaning from rocks and large pieces of ash as they accumulat...

Page 11: ...3 The boiler is fireproof The temperature of its outer surfaces does not exceed the normalized values but during its operation the gas flue pipes and chimney are heated to a high temperature In order...

Page 12: ...y walls the presence of foreign objects in the chimney very fine coal dust coal is used low quality fuel is used a large amount of ash on the grates or in the ashpit fuel stall in the bunker Clean the...

Page 13: ...pacity It is recommended to carry out preventive cleaning of the boiler heat exchanger every 2 months 11 4 The heat exchanger cleaning is done by pulling the upper removable part of the bunker 13 by i...

Page 14: ...of steam and hot water boilers with a steam pressure of no more than 3 kgf cm2 hot water boilers water heaters with water heating temperature not higher than 75 EN 303 5 2012 GOST 20548 TC 4931 007 8...

Page 15: ...echnical operation Date The result of the examination Date of the next examination Signature of the person responsible 6 1 Registration The UNIVERSAL RG boiler______________________ water heating is r...

Page 16: ...e boiler into operation Repeated call in a specialist is paid by the buyer Terms of warranty validity Acceptance of the boiler into operation should be carried out only with the participation of an au...

Page 17: ...a i ja ekspluateerimisreeglite rikkumine v ib ajendada tarbimisomaduste alandust v i t rge ja sama garanteerimisremonti iguse kaotamine Tehas tegija sama teeb t iendava seadmete hange mis pole l litat...

Page 18: ...kuud ekspluatatsioonip eva sisse l litamiseks vaid mitte rohkem kui 24 kuud m gip evast Palume Teid j rgida alltoodud n udmisi ja k igepealt igaaastase kontrolli l biviimist ja spetsialiseeritud orga...

Page 19: ...P LETAMISE KORD 8 6 5 KATLI PEATAMISE KORD 8 6 6 KATLI EKSPLUATEERIMINE 9 7 S STEEMI KATSED KAITSEVAHENDEID 9 8 MONTAA I TEENINDAMISE JA EKSPLUATEERIMISE OHUTUSREEGLID 10 9 KATLI T KORRASTUSED JA NEND...

Page 20: ...liruumise k rgel mitte v hem kui 2 8 m Katli installeerimine soojustatud ruumi v ljaspool katli soojusisoleerimine ja sama k ikide torustiku igustamata soojukaotamise ja kiire s steemi mberk lmetamise...

Page 21: ...ub ruumide soojustusest 5 Koostis ja t p him tted Katli skeem on toodud Joones 1 1 Tuhakasti uks 12 Bunkri alamosa mahav tmise k epidemed 2 huservi regulaator 13 lem mahav tmise bunkri osa 3 P letamis...

Page 22: ...EN 303 5 2012 k esoleva juhend ja katli pass 3 kgs ruutsm veesoojuskatlite ja veesoojuste mis veetemperatuur mitte k rgem kui 85C seadme reeglid Kuuma vee ja auru torustiku ohutu ekspluatatsiooni sea...

Page 23: ...ti ukse kaudu ilma soojusvahetuste demontaa iga kui ka tuhakasti leval p rast soojusvahetuse demontaa i 6 3 2 Tehas tegijaga katli omanike n udega tehakse remondikomplektede toomine tuharestide vahe t...

Page 24: ...huservi regulaator kinni 2 ja avame alam huetteanne regulaator 4 teeme katsete kaudu l tku veetemperatuur ei pea letama 75 kraadi 6 6 Katli peatamise kord 6 6 1 J rguline katli peatamine toimub 1 p e...

Page 25: ...e huimejate eemaldamisega gaasiteedel gaasikogus ja suitsuk ijal suitsutorul j tkukoha kvaliteetse keevitamise arvelt Imimese v ltimiseks suitsuteede puhastamisluuk gaasitee risisestus konomaaiser ja...

Page 26: ...ise leva k va taldatega jalatsitega 8 5 N op letuse v ltimiseks on keelatud katli katust v lja v tta levaade v i k tuse bunkrisse allalaadimise tuhakasti avatud uksega 8 6 On keelatud kasutada p letav...

Page 27: ...s tekkib tahmi ja t rvu mis alandab soojusvahetust ja tema j udsus Soovitatakse ks kord 2 kuu p rast teha profilakteerimis katlipuhastust soojusvahendus 11 4 Soojusvahenduse puhastamine toimub lema pu...

Page 28: ...haseline ___________ on tehtud vastavalt n udmisele Seadme reeglid ja ohutu auru ja veesojendamise aurur huga mitte rohkem kui 3 kgs cm2 veesoojendamiskatlid veesojendajad veesojenda temperatuuri mitt...

Page 29: ...kontrolli mise kuup eav Allkiri 5 2 Tehnilise ekspluatatsiooni ja korraliku seisundi vastutav isik Kuup ev Tunnustamise tulemus J rgmise tunnustamise kuup ev Vastutava isiku allkiri 6 1 Registreerumi...

Page 30: ...se eest maksab ostja Garantiikohustuse kehtestumise tingimused Katli ekspluatatsioonisse v tmine peab olema tehtud ainult vastava spetsialisti osalemisega Katli ekspluateerimisel on kohustuslik igaaas...

Page 31: ...UNIVERSAL RG EN 303 5 2012 4931 007 82749029 2007 4931 008 82749029 2007 www Ritek ee...

Page 32: ...2 EN 303 5 2012 20548 4931 007 82749029 2007 24 EN 303 5 2012 30735 2001 4931 008 82749029 2007 18 24...

Page 33: ...3 1 4 2 4 4 5 5 5 6 6 6 1 6 6 2 7 6 3 7 6 4 8 6 5 9 6 6 9 7 10 8 11 9 11 10 12 11 13 12 14...

Page 34: ...1 UNIVERSAL RG EN 303 5 2012 4931 007 82749029 2007 4931 008 82749029 2007 1 2 2 4 80 1 3 1 4 1 5 1 6 1 7 2 8 1 8 1 9 0 7 1 10 UNIVERSAL RG 1000 2 2 1 UNIVERSAL RG 3 3 1 1 1 1 1 1 1 4 4 1 750 650 750...

Page 35: ...3 4 4 4 5 84 4 6 6000 70 80 1 200 1 10 30 4 7 c 40 8 24 36 5 1 1 12 2 13 3 14 4 15 5 16 6 17 7 18 8 19 9 20 10 21 11 22 23 24 25 900 3 250 400 750 930 900 2040 57 200 40 132 0 01 13 18 19 20 21 22 23...

Page 36: ...4 1 14 18 21 20 5 4 2 13 9 23 19 24 25 21 20 1 23 2 2 4 5 4 16 20 17 20 3 5 5 9 6 UNIVERSAL RG 10 574 03 18 06 2003 EN 303 5 2012 3 2 85 3 05 05 3 01 01 217 31 01 04 27303 01 6 1 6 1 1 22 6 1 2 22 0...

Page 37: ...7 17 20 15 6 1 3 6 1 4 6 1 5 6 1 6 6 2 6 2 1 39 Pa 2 6 1 6 2 2 1 2 1 5 6 2 3 45 6 2 4 8 6 3 6 3 1 20 6 3 2 2 2 6 4 6 4 1 6 4 2 0 5 1 1...

Page 38: ...8 10 6 4 3 6 3 4 6 4 5 6 5 6 5 1 6 5 2 6 5 3 6 5 4 4 5 20 6 5 5 20 2 50 70 6 5 6 6 5 7 6 5 8 6 5 9 15 30 15 5 6 5 10 30 6 5 11 2 6 5 12 600 6 5 13 2 4 75...

Page 39: ...9 6 6 6 6 1 1 6 6 2 850 6 6 3 2 4 90 6 6 4 6 7 6 7 1 UNIVERSAL RG 6 7 2 2 3 10 15 2 6 7 3 13 9 2 4 40 6 7 4 1 8 6 7 5 1 6 7 6 750 60 6 7 7 100 200 20 6 7 8 6 7 9...

Page 40: ...10 6 7 10 6 7 11 6 7 12 7 7 1 100 10 2 UNIVERSAL RG 3 2 7 2 7 3 7 4 7 5 3 2 850 7 6 7 7...

Page 41: ...11 8 8 1 8 2 8 3 8 4 8 5 8 6 8 7 10 10 8 8 8 9 0 1 8 10 8 11 8 12 8 13 8 14 34 03 301 87 139 87 9 95 20...

Page 42: ...12 10 10 1 10 2 10 1 10 3 11 11 1 11 2 11 3 2 11 4 13 11 5 11 6 11 7...

Page 43: ...______________________________ _________________132___________________ 2 1 Universal RG ___________ 3 2 750 EN 303 5 2012 20548 4931 007 82749029 2007 30735 2001 4931 008 82749029 2007 ______ ________...

Page 44: ...14 3 4 3 3 5 4 1 5 1 5 2 6 1 UNIVERSAL RG _____ ____________________201____ ____________ ___________________ __________ _____________ ____________________________________ __________________...

Page 45: ...15 EN 303 5 2012 20548 4931 007 82749029 2007 24 100 ___________________20___...

Reviews: