1. Prepare site

: Ensure the 

enclosure meets the dimension 
requirements and check the 
gas and electrical supplies have 
been prepared according to the 
information in this guide.

Ensure there are no walls, studs, 
noggins, ceiling joints, wiring, 
or other obstructions within the 
wall or ceiling cavity where the 
flue is to be located.

2. Assemble zero clearance 
box

: Refer separate assembly 

instructions included with the 
zero clearance box.

3. Fit zero clearance box

: Slide 

assembled box into the cavity, 
ensuring the gas and electrical 
supplies are accessible.

4. Install flue

: Install flue kit 

and/or components, refer p. 22 
for an overview of how all the 
components fit together.

5. Unpack engine

: The 

Compact 2 engine is supplied in 
one carton. Check for damage 
and ensure you have the correct 
gas type before starting. Do not 
install if any damage is evident.

6. Prepare engine

: Attach the 

flue guide rails, supplied with 
the zero clearance box, to the 
top of the heater engine using 
the four predrilled holes and 
screws supplied.

Remove and put aside the flue 
access plate and gas/electrical 
plate.

7. Fit cladding

: Before installing 

the heater ensure the cladding 
for the front of the enclosure 
has been fitted. The cladding 
MUST BE installed flush with 
the zero clearance box. Failure 
to do this will cause alignment 
problems with the flue.

8. Connect flue adaptor

Connect the flue adaptor* to 
the engine by aligning the guide 
rails with the guide plate* of 
the flue adaptor. Slide the flue 
adaptor in until the guide plate 
is fully home against the rear of 
the flange of the heater at the 
top of the heater.

* Supplied with the zero clearance box

9. Position engine

: Place the 

Compact 2 engine in front 
of the fireplace enclosure. 
Use a panel of the cardboard 
packaging underneath the 
engine to minimise damage to 
the floor.

10.

 

Connect electrical supply

Plug in the 3-pin connector of 
electrical connection inside the 
fireplace.

11. Insert unit into fireplace

Carefully move the heater into 
the fireplace ensuring the gas 
supply pipe and fittings feed 
into the rear access hole.

12. Connect flue

: The weight 

of the flue should not be 
supported by the appliance, 
it should be self-supporting. 
Supporting the flue is usually 
completed during the framing 
stage with flue supports or 
straps within the cavity.

13. Secure flue

: Replace the 

flue access plate and secure the 
guide plate of the flue adaptor 
to the flue access plate with the 
two screws supplied.

Secure access plate to the 
heater.
 

14. Connect gas supply

Connect gas supply pipe and 
fittings to the gas control valve 
inlet and tighten.

15. Secure heater

: Fasten the 

heater to the cladding using 
appropriate fasteners (not 
supplied). There are three holes 
across the top of the front 
assembly mounting panel, and 
side panels.

16. Leak test

: Leak test all 

appliance connections. When 
finished remove any residue 
with a rag. Prevent any soapy 
solution coming into contact 
with the electrical components.

12. Complete installation

Refer to instructions on p. 18.

Inbuilt mock chimney 

(zero clearance installation)

Summary of Contents for Compact 2 RIBF2L

Page 1: ...ation guide Models RIBF2N RIBF2L Standard frame Traditional frame Installer please note The gas and electrical plate of the unit is not required when attaching the traditional frame refer p 18 for fur...

Page 2: ...For installations into a combustible opening a Rinnai zero clearance box and flue kit are mandatory Appliance must be installed with a Rinnai approved flue system This appliance shall be installed in...

Page 3: ...ion 8 Electrical connection 9 Flueing options 10 Flueing guidelines 11 Masonry flue installations 12 Masonry installation 14 Inbuilt mock chimney 16 Completing the heater installation 18 Flame pattern...

Page 4: ...is distributed from the top of the appliance Data plate Inside appliance on the front right hand side panel Gas connection BSPF male flare enters from the rear of the appliance Ignition Continuous sp...

Page 5: ...y of sand and cement to level the base as required Minimum clearance required from the spigot to the back of the fireplace is 50 mm p 12 Inbuilt mock chimney W width 685 mm H height 615 mm D depth 380...

Page 6: ...g it is recommended that a mat be placed in front of this appliance Mantels and surrounds Combustible mantels and surrounds require clearance from the unit to minimise the risk of fire Mantels and sur...

Page 7: ...nce area around the Compact 2 without having the unit on site Glass width 500 300 300 420 300 Clearance Clearance Minimum above fire Minimum to ceiling 1100 1000 Compact 2 standard frame Glass width 5...

Page 8: ...n of the heater Gas supply location 1 Mark off the location for the vertical centre line of the heater enclosure 2 To the right of the vertical centre line mark off both the vertical and horizontal lo...

Page 9: ...d plug assembly through the front panel With the frame assembly removed redirect the cord and plug assembly with grommet underneath the heater to the front of the unit either left or right hand side C...

Page 10: ...mney offset wall penetration For installations into a combustible opening with a zero clearance box Flue runs in wall then penetrates the building before terminating vertically Typically used in multi...

Page 11: ...quate flue systems depending on the installation Minimum clearances are shown in AS NZS 5601 1 Flue terminal locations Must be compliant with Clearances Required for Flue Terminals from AS NZS 5601 1...

Page 12: ...result Sealed means no holes or openings in the fireplace Some criteria for checking chimney soundness Rinnai strongly recommends the use of a Rinnai flexiliner flue system Failure to meet this crite...

Page 13: ...Installation Installation servicing and repair shall be carried out only by authorised personnel...

Page 14: ...crew the five screws securing the gas electrical plate and put aside 5 Connect flue adaptor Connect the flue adaptor to the flexiliner flue 6 Position engine Place the Compact 2 engine in front of the...

Page 15: ...ue spigot adaptor Attaching the flexiliner flue to the unit 1 Attach the guide rails to the heater using the predrilled holes and four screws 2 Align the guide plate with the guide rails and slide the...

Page 16: ...aligning the guide rails with the guide plate of the flue adaptor Slide the flue adaptor in until the guide plate is fully home against the rear of the flange of the heater at the top of the heater Su...

Page 17: ...ble the zero clearance box 3 Fit zero clearance box 6 Prepare heater engine 7 Fit cladding 8 Connect flue adaptor 13 Secure flue 15 Secure the heater Guide rails Flue access plate Gas electrical acces...

Page 18: ...enhance the realistic log burning look of the heater Do not force or block the burner ports with the granules and do not place any granules on the rear burner 4 Replace combustion chamber glass and t...

Page 19: ...anules 1 Removing the combustion chamber glass panel Glass clamp Retaining screw Retaining screw Front feet as pivot points Test point screw Regulator Rear view of installed frame Top fold Frame assy...

Page 20: ...d gas injectors or log set burn media has shifted from when the fire was first installed There are some warning signs that could indicate a problem Unusual smell from the appliance Continued difficult...

Page 21: ...1 220 240 v 50 Hz BR G Y BL W W BL BL W IGN SWITCH MICR O BL SPAR KER ELECTRODE FAN 2 BR FAN SWITCH ON OFF THE R MAL 1 2 3 R BL BL R W FAN SWITCH HI LOW MICR O W S V OHS TC W R Red BL Blue BR Brown W...

Page 22: ...ew of how all the components are fitted together and to illustrate important installation points Zero clearance box assembled and installed N B only partially shown in this image Flue adaptor connecte...

Page 23: ......

Page 24: ...Rinnai co nz Experience our innovation 0800 746 624 http www youtube com rinnainz Compact 2 installation guide 11817 D 04 15...

Reviews: