Start-up, calibration and operation of the burner
6.8
Adjustment pressure switches
6.8.1
Air pressure switch - CO check
Adjust the air pressure switch after having performed all other
burner adjustments with the air pressure switch set to the start of
the scale (Fig. 37).
With the burner working at MIN output, insert a combustion
analyser in the stack, slowly close the suction inlet of the fan (for
example, with a piece of cardboard) until the CO value does not
exceed 100 ppm.
Slowly turn the appropriate knob clockwise until the burner goes
into lockout.
Check the indication of the arrow pointing upwards on the gradu-
ated scale.
Turn the knob clockwise again, until the value shown on the grad-
uated scale corresponds with the arrow pointing downwards, and
so recovering the hysteresis of the pressure switch (shown by the
white mark on a blue background, between the two arrows).
Now check the correct start-up of the burner.
If the burner locks out again, turn the knob anti-clockwise a little
bit more.
6.8.2
Maximum gas pressure switch
Adjust the maximum gas pressure switch after having performed
all the other burner adjustments with the maximum gas pressure
switch set at the end of the scale (Fig. 38).
With the burner operating at maximum output, lower the adjust-
ment pressure by slowly turning the relative knob anticlockwise
until the burner locks out.
Now turn the knob clockwise by 0.2 kPa (2 mbar) and repeat the
start-up of the burner.
If the burner locks out again, turn the knob clockwise again by
0.1 kPa (1 mbar).
6.8.3
Minimum gas pressure switch
Adjust the minimum gas pressure switch after performing all the
other burner adjustments with the pressure switch set to the start
of the scale (Fig. 39).
With the burner operating at maximum output, increase adjust-
ment pressure by slowly turning the relative knob clockwise until
the burner stops.
Now turn the knob anticlockwise by 0.2 kPa (2 mbar) and repeat
burner start-up to ensure it is uniform.
If the burner locks out again, turn the knob anti-clockwise again
by 0.1 kPa (1 mbar).
6.8.4
Pressure switch PVP kit
Adjust the pressure switch for the valve leak detection control de-
vice (PVP kit) (Fig. 40), if present, according to the instructions
supplied with the kit itself.
WARNING
1 kPa = 10 mbar
Fig. 37
D3854
Fig. 38
D3856
Fig. 39
D3855
Fig. 40
D3855
Summary of Contents for RLS 650/E MX
Page 2: ...Translation of the original instructions ...
Page 44: ...20027766 42 GB Appendix Electrical panel layout ...
Page 45: ...43 20027766 GB Appendix Electrical panel layout ...
Page 47: ...45 20027766 GB Appendix Electrical panel layout ...
Page 48: ...20027766 46 GB Appendix Electrical panel layout 0 1 1 1 ...
Page 49: ...47 20027766 GB Appendix Electrical panel layout 0 ...
Page 50: ...20027766 48 GB Appendix Electrical panel layout 0 0 0 1 0 2 0 0 0 0 0 0 0 30 3 3 0 0 1 0 ...