3.3 Hydraulic unit construction
The hydraulic diagrams sketched below serve as a planning aid and to illustrate a possible system layout. All
the components shown outside the chiller and the hydraulics to be provided by the customer must be
planned and designed by the planner or the specialist company carrying out the work.
bauseitige Hydraulik
1
1: Hydraulics provided by the customer
Configuration:
Chiller with plate heat exchanger for hydraulic separation of primary and secondary circuits. Use of glycol-
water mixture on primary side and water on secondary side possible. Secondary circuit pump required. Note
the minimum medium volume on the primary side.
bauseitige Hydraulik
1
1: Hydraulics provided by the customer
Configuration:
2 chillers in redundant unit operation with a common storage tank as hydraulic compensator. Use of glycol-
water mix in complete system. Storage tank dimensioning based on the cooling capacity of the units.
REMKO KWE Eco series