Intended Use

This product is intended to be used for the lifting of 
goods, the lifting of personnel, rope access or for 
providing a safety anchor for the prevention of falls. 

It is expected that all users of this product have the 
necessary medical and physical capabilities, are fully 
trained and competent in its safe assembly and use. 

Inspection Prior to Initial Operation

This product must be inspected prior to initial 

operation by a competent person to ensure that the 

structure is safe and that it has not been damaged 

by incorrect assembly, transport or storage. 

Inspection Before Starting Work

Before starting work, the assembly of the product 
and all load-bearing components should be 
checked for visual defects. This includes checking 
the integrity of all profiles for denting, making sure 
there is no wear or elongation on the bolt holes 
and ensuring that the trolley moves freely along 
the beam.

Correct Operation

    

Only raise and lower loads when castor brakes 
are engaged 

    

Do not allow the load to swing

    

To avoid side pull, lowering and lifting should 
only be carried out when the load chain forms 
a straight and vertical line between the load 
and lifting attachment point on the trolley. 
(Refer to figure A)

    

We recommend the use of load-sensing or 
overload protection devices on all lifts

    

The risk assessment and method statement 
must take into account any factors that might 
apply additional loading to the system during 
lifting operations

    

Take care when transporting and storing the 
system to avoid damage

    

To ensure stability of the structure, the 
operating span of the beam must be equal 
to or greater than the distance between the 
castors on the A-Frame.

Warning

    

The equipment should not be used outside 
of its limitations, or for any purpose other than 
that for which it is intended

    

Do not lift or transport loads while personnel 
are in the danger zone 

    

Do not allow personnel to pass under a 
suspended load 

    

Never leave a suspended load unattended

    

Do not start moving the load along the beam 
until you have checked that it has been 
attached correctly

    

Don’t allow the load to hit the system frame

    

When winching, only use one winch with each 
sheave and make sure they never cross paths 
with each other 

    

Be aware of any adverse weather conditions 
such as strong or gusty winds which could 
impose additional horizontal loads and affect 
the stability of the structure. Stop using if 
weather is impacting on lifting, and either 
disassemble the gantry or tie it to a rigid 
structure to ensure it can’t overturn

    

Be aware of hazards when setting up/folding 
down, such as trapping fingers in rotating 
parts

Traversing the Load

Due to a high modulus of elasticity in aluminium, 
when loaded the gantry beams will deflect. 
This is perfectly normal for our products. Using 
aluminium enables us to achieve the highest 
levels of strength to weight ratio, which is an 
important feature of portable gantries. The level of 
deflection will be determined by the span length 
and the beam profile that is being used, as well as 
the weight of the load being lifted.

Before traversing loads on the 

PORTA

GANTRY, it 

is important to take in to account the following; 

    

Only use appropriate REID trolleys to move the 
load on the beam. 

    

When moving a loaded trolley along the 
beam, move the load steadily and in a 
controlled manner. Do not apply an excessive 
force to try and move the load if it does not 
move easily.

    

Depending upon the beam section (A, B or 
D), beams will deflect when loaded. 

This is 

normal. 

The greater the load, the greater the 

deflection. Please refer to our beam deflection 
table for more information. Deflection must be 
taken into consideration when planning the lift.

    

Any traversing of loads along the beam must 
be performed in a controlled manner to ensure 
complete stability of the structure throughout 
the operation. 

Maximum Capacity

Goods Lifting:

 This product is designed to lift 

and lower loads up to its rated capacity. Do not 
exceed the working load limit indicated on the 
product. 

Personnel Lifting: 

When lifting people, the 

overall load limit is reduced by half to provide an 
increased safety factor. The maximum capacity 
permitted by the personnel winch/accessory used 
in conjunction with this product also needs to be 
considered.

Temperature Range

This product can be operated in ambient dry 
temperatures between –20°C and +55°C (-4°F 
and 131°F). Consult your supplier in case of 
extreme working conditions.

Notes for Correct Operation 

    

Assemble only as instructed (ensure all 
bolts are present and fitted correctly as per 
instructions) 

    

Suitable, appropriately rated winches and 
connection plates must be used for all 
applications

    

The product should be set up at a safe 
distance from the hazard or lift area, before 
moving the structure into place 

    

The supporting ground/structure where 
the gantry is to be used must be stable 
and capable of withstanding the maximum 
expected load applied during use

    

We recommend that gloves are worn when 
using the equipment

    

The beam must be horizontal prior to any lift 
and A-Frames vertical and parallel to each 
other 

    

Do not use the product if the trolley does 
not run freely along the beam. (For certain 
applications, such as when the system is being 
used as a restraint point, the trolleys can be 
locked into position) 

    

Attach the hoist to the lifting point on the 
trolley only, making sure it is attached in a way 
that does not expose the user to danger by 
the hoist, chain or load

A

Summary of Contents for porta-gantry 1000

Page 1: ...REIDLIFTING COM Assembly Operation Guide PORTAGANTRY 500 3000...

Page 2: ...Portable Safe Please read the following instructions and guidance notes carefully before using or operating the system They contain important information about how to handle and use the system in a sa...

Page 3: ...in rotating parts Traversing the Load Due to a high modulus of elasticity in aluminium when loaded the gantry beams will deflect This is perfectly normal for our products Using aluminium enables us to...

Page 4: ...ver is lower To be able to effectively and safely move loads above these limits the operator should use the most appropriate mechanical aid For further advice please contact REID Lifting or a qualifie...

Page 5: ...nt of the system before beginning work When using the product as a fall arrest anchor ensure there is adequate fall clearance when working at height refer to figure C A competent person should calcula...

Page 6: ...inspections every 6 months for personnel lifting and every 12 months for goods only unless adverse working conditions or profile of use dictate shorter periods The components of the system frame need...

Page 7: ...ity build up leading to an incentive spark Although the risk of such ignition is unlikely the system must be earthed during assembly and use This can be achieved by attaching an earthing lead to a con...

Page 8: ...ket 24mm combination spanner 14mm long series allen key 14mm Hex key socket Apply the castor brakes Put brakes on only with protective footwear ensuring that the castors are in the orientation shown T...

Page 9: ...when gantry is fully erect This avoids a working at height problem when attaching a hoist Keep hands clear of potential Pinch area marked with warning tape in the scissoring system The chain hoist mu...

Page 10: ...om the center of the beam Beam height adjustment bolts 2 bolts on each upright Tighten all bolts to 27 Nm 20 ft lbs or until spring washers are fully depressed Assembly Instructions Insert and tighten...

Page 11: ...and stored in a clean and dry manner The jack leg should be lubricated with EP2 grease on the internal thread and gears at regular intervals up to 6 months maximum depending on service conditions Vari...

Page 12: ...ointed beams together ensuring the internal guide blocks are aligned correctly 2 Connect the chain block to the shackle on the cheek plate as shown Release the load chain until reaching the master lin...

Page 13: ...guide blocks are aligned correctly 2 Dimensions Beam length Beam adjustment Clear operating span Height to lifting eye Height increment Height to top of beam Width Height to top of roller PORTAGANTRY...

Page 14: ...27 8 x 200 R 3927 5848 5930 4330 2733 97 82 200 PGAS01000TC1 5829 9 x 200 R 4029 6149 6231 4431 2733 102 82 200 Dimensions mm Frame size Product Code DMax Height to lifting eye E Height increment DMin...

Page 15: ...nce with the IRATA Code of Practice by doing so contributes to promote the development of safe systems All product names are trademarks of REID Lifting Ltd PORTADAVIT PORTABASE PORTAQUAD PORTAGANTRY R...

Page 16: ...ystem Ensure the pin is fully engaged 1 Product Number 2 Serial Number 3 WLL 4 Year of Manufacture 5 Standards 6 ATEX 7 Max Moment The system is not suitable for fall arrest applications The system is...

Page 17: ...The goods capacity WLL of the device The year of manufacture The standards to which the device is approved The ATEX rating of the product if applicable CE Marking Minimum braking load MBL Insert data...

Page 18: ...35 PORTAGANTRY 500 3000 Notes Notes...

Page 19: ...nquiries reidlifting com www reidlifting com Printed using environment friendly processes and materials All information herein is copyright protected by REID Lifting Ltd All company and product names...

Reviews: