REID LIFTING PORTA-DAVIT 500 Series Assembly & Operation Download Page 7

Tel: +44 (0)1291 620796   www.reidlifting.com

specialist workshop that uses original spare parts. 
It is recommended that once inspected the device is 
marked with the date of next inspection.

Inspections are instigated by the user.  
If detailed information is required on inspection  
and test criteria, please refer to your supplier’s 
technical department.

Please refer to page 19 for the equipment  

Inspection Record.

If using the davit in explosive atmospheres see 
additional section titled ATEX - page 9. 

Maintenance/Repair

In order to ensure correct operation, not only the 
operating instructions, but also the conditions for 
inspection and maintenance must be complied with.  
If defects are found 

stop

 using the davit immediately.

No alterations or additions to the equipment 
should be made without the written consent of the 
manufacturer. Any repair shall only be carried out in 
accordance with the manufacturer’s procedures.

It is recommended to maintain the equipment in a 
clean and dry manner. Cleaning is suggested using a 
sponge or cloth with warm, soapy water (using diluted 
domestic washing up liquid), rinsing and allowing to dry.

The majority of the structure is constructed from 
aluminium with steel fasteners; non-metallic parts are 
constructed from acetal co-polymers, polyethylene 
and polyester.

Storage and Transportation

The 

PORTA

-DAVIT 500 and its accessories are to be 

stored and transported in the bags provided.

When transporting the components the user must 
take note of the manual handling considerations.

SOCKETS 

The 

PORTA-

DAVIT 500 structure needs to be anchored 

to a surface/foundation capable of withstanding the 
applicable loading. The davit can be supplied with one 
of the sockets specified below

 (only sockets supplied 

by REID Lifting are approved to be used with the 

PORTA

-DAVIT 500):

Top 

Mount

Side 

Mount

Bridge 

Mount

•  

 The 

Top Mount

 socket is for use on flat horizontal 

surfaces. It can be installed onto concrete using 
resin bonded anchors or into steel work using bolts

• 

The 

Side Mount

 socket can be installed using resin 

bonded anchors or mechanical anchors

•  

 The 

Bridge Mount 

socket is for mounting into steel 

work and walkways

• 

The 

Cast & Resin Bonded

 sockets can be cast 

into  new concrete or resin bonded into existing 
concrete

Socket Installation

Depending upon the socket type there are multiple 
ways that installation can be achieved. When using 
bolts they are to be minimum grade 8.8 BZP or if 
stainless, grade A4 or equivalent.

When installing the socket it is important to 
ensure that the top face is as level as possible, with 
installation being not more than 3 degrees misaligned 
from the horizontal.

Socket installation should only be carried out by a 
competent person.  If specifying the anchors, resin, 
fasteners or any combination of the afore-mentioned,  
it is essential that the competent person is of ability  
to specify an installation that is safe for use.  If in any  
doubt about the calculation of loads contact your  
REID Lifting representative. 

Cast & Resin 

Bonded

Summary of Contents for PORTA-DAVIT 500 Series

Page 1: ...Tel 44 0 1291 620796 www reidlifting com www reidlifting com Assembly Operation ASSEMBLY VIDEO...

Page 2: ...ENANCE Regular Inspections Maintenance Repair Storage and Transportation SOCKETS Socket Installation Verifying the Installation MARKING ATEX ATEX Classification ATEX Identification ATEX Spark Formatio...

Page 3: ...work with the PORTA DAVIT 500 must read the operation instructions and act accordingly Operation including preparation trouble shooting during operation and cleaning Maintenance inspection repair Tra...

Page 4: ...ft and lower loads up to its rated capacity The capacity indicated on the product is the maximum working load limit WLL or safe working load SWL which must not be exceeded definition is country depend...

Page 5: ...t use the davit if it does not rotate freely in the bearing or the bottom flange is fouled in any way preventing free rotation of the davit Do not knot or shorten the tension strap to reduce operating...

Page 6: ...uipment Regulations 1998 S I 1998 No 2306 EN795 2012 The Lifting Operations and Lifting Equipment Regulations 1998 S I 1998 No 2307 The safety regulations of the respective country for using manual li...

Page 7: ...in the bags provided When transporting the components the user must take note of the manual handling considerations SOCKETS The PORTA DAVIT 500 structure needs to be anchored to a surface foundation...

Page 8: ...tion has the ultimate capacities required Following initial socket installation verification tests we do not recommend overload tests for the socket or davit and suggest thorough visual examination on...

Page 9: ...use in Zone 1 Environments II 2 GD T6 IIdentification for protection against explosions II Unit group II non mining application 2 Category 2 High safety for use in Zone 1 GD For use in gas G dust D at...

Page 10: ...rging Additionally the kingpin should be checked to ensure it rotates freely and the lower bearing must be ensured to be fixed to the structure with no possibility of a build up of debris between the...

Page 11: ...is optional and the socket type may vary between a Top Mount Side Mount Bridge Mount Cast In or Resin Bonded depending on application N B No tools are required for assembly ASSEMBLY INSTRUCTIONS Glov...

Page 12: ...s in full contact with the socket flange N B Fits all REID Lifting socket types flush mount top mount side mount bridge mount and the PORTA BASE Demonstrated using a top mount socket 3 Loosen the reta...

Page 13: ...with a PORTA BASE mobile socket the pin must be inserted within the yellow zone which gives a maximum operating radius of 1000mm If used with fixed sockets any adjustment position can be used giving...

Page 14: ...version 2 Remove retaining pins and clips then feed winch rope hook end over sheaves The winch should not be attached at this point The winched option version of the davit has a rigid adjustment chann...

Page 15: ...to davit base with adjustment pin 6 Insert retaining clip through adjustment pin 7 Position winch on rigid adjustment channel and attach winch with retaining pins and clips Ensure winch rope is wound...

Page 16: ...situation needs to be carefully considered Method A 2 People Recommended 1 Assemble PORTA DAVIT 500 or PORTA DAVIT 350EX on the floor horizontally adjacent to the fixed socket position and attach the...

Page 17: ...jib arm in line with upright tube and tighten the retaining strap 4 Rotate the davit into a vertical position adjacent to the socket 5 Two people should lift the davit assembly 500mm and insert the ki...

Page 18: ...t names are trade marks of REID Lifting Ltd PORTA GANTRY PORTA GANTRY RAPIDE PORTA DAVIT PORTA BASE T DAVIT PORTA QUAD THE QUEEN S AWARDS FOR ENTERPRISE INTERNATIONAL TRADE 2018 QUALITY SAFETY E OE Qu...