Removing and installing conveyor belt
- Disconnect hydraulic connectors and remove spreader by loosening screws (2).
- Disconnect the suspension and coupling by loosening screws (1).
- Relax the conveyor belt on both sides by loosening the nuts (3).
- Remove connecting screws (10) to the hopper (11).
- Loosen and remove the tension rings of the bearing (4) (in the direction of movement to
the right).
- Release screws on side panel (5) and remove completely, including bearing (6).
- Remove conveyor belt.
For installation, do the process in reverse.
Fig.8: Removing and installing conveyor belt
Tensioning the conveyor belt after installation
- When the conveyor belt is relaxed, mark a length of 1000 mm on both sides of the
conveyor belt.
- Tighten the conveyor belt evenly on both sides using the two tension screws (see page
14) until the marked length is stretched to a maximum of 1003 mm.
- Run in the conveyor belt for approx. 30 minutes until it runs in the middle between the
side guides and readjust if necessary.
The conveyor belt must not touch the sides, otherwise it will be damaged.
When readjusting the conveyor belt on the side, retighten gradually, where
the belt touches.
Too much tension will shorten the service life of the conveyor belt!