16
REC Installation Manual - REC Alpha Panels - IEC 61215 /61730
Rev 13 - 11.22
SIX-POINT MOUNTING
These instructions are applicable to the following products only:
• REC Alpha Pure Series
A six-point mounting configuration secures the panel on three continuous rails (or other support structures) with three clamps on each side of the panel in
the zones marked below:
GR
GR
GR
GR
760 mm [29.9 in] - 840 mm [33.1 in]
100 mm [3.9 in] - 430 mm [16.9 in]
430 mm [16.9 in] - 100 mm [3.9 in]
CAUTION
• The middle rail must not be installed on the side of the junction box where the cables exit.
• A total of three continuous rails (or other support structures) must be used to secure the panel.
• The center point of each clamp and the minimum grip length must be fully located within the marked zone to be rated to the given value
(fig. 12).
Rail positioning
Legend
Clearance Gap
Clamping zone
20-40 mm
40-60 mm
>60 mm
Test Load
(Design Load)
Test Load
(Design Load)
Test Load
(Design Load)
100 - 430 mm
+2000 Pa / -2000 Pa
*
(+1333 Pa / -1333 Pa)
+6300 Pa / -6000 Pa
*
(+4200 Pa / -4000 Pa)
+8000 Pa / -6000 Pa
*
(+5333 Pa / -4000 Pa)
760 - 840 mm
Once a module is secured as described above (fig. 24), additional clamps, i.e., ≥7, may be freely located on panel frame without
affecting the warranty. Loads marked with a
*
were not certified as part of IEC 61215/61730 testing; these have been evaluated by
REC’s internal testing process.
Rail position
Fig. 12: Six-point mounting configuration clamping zones: REC Alpha Pure Series
Legend
Clearance Gap
Clamping zone
20-40 mm
40-60 mm
>60 mm
Test Load
(Design Load)
Test Load
(Design Load)
Test Load
(Design Load)
100 - 400 mm
+2000 Pa / -2000 Pa
*
(+1333 Pa / -1333 Pa)
+6300 Pa / -6000 Pa
*
(+4200 Pa / -4000 Pa)
+8000 Pa / -6000 Pa
*
(+5333 Pa / -4000 Pa)
820 - 910 mm
Once a module is secured as described above (fig. 24), additional clamps, i.e., ≥7, may be freely located on panel frame without
affecting the warranty. Loads marked with a
*
were not certified as part of IEC 61215/61730 testing; these have been evaluated by
REC’s internal testing process.