41
FUTERA II START UP SHEET
Date of Start Up:
RBI Ref. #:
Serial # ('s):
Boiler
#1
Model#
Boiler
#2
Boiler
#3
Boiler #4
Boiler
#5
The above information will be used to identify each boiler in the system. You should make every attempt
to affi x the boiler number as noted here to the boiler physically.
START UP PROCEDURE AND DATA
Readings Or Checks By Boiler Number
STEP DESCRIPTION
1 2 3 4 5
1
No leaks, valves open, pump running, exchanger full
2
Gas lines purged, no leaks, no missing test plugs
3
Manometer installed in test port upstream of fi ring valve
4
Manometer installed to air box pressure tap
5
Wiring checked and verifi ed with supplied diagram
6
All terminals identifi ed properly and tight
7
Fan (no gas): Verify no air leaks through outer cabinet
8
With fan running: Record air box pressure "W.C."
9
With fan running: Record back pressure "W.C."
10
Vent confi guration (HOR: horizontal VER: vertical)
11
Equivalent vent length (each fi tting is 10' equivalent)
12 Breaching
size:
13 Barometric
installed/location:
14
Through wall venting with factory supplied termination:
15
Pilot adjusted to within 1 turn of max (natural gas only)
16
Spark is strong and continous w/o gas:
17
Pilot fi res-advances to main several times (main gas off)
18 Voltage:
19
Manifold pressure "W.C." (see tag on boiler) High Fire
20
Manifold pressure "W.C." (see tag on boiler) Low Fire
21 O
2
Lo Fire%
22 O
2
Hi Fire %
23 CO
2
Lo Fire %
24 CO
2
Hi Fire %
25
CO Lo Fire PPM
26
CO Hi Fire PPM
27
Effi ciency Lo Fire %
28
Effi ciency Hi Fire %
29 Inlet
Temp
(F)
30 Outlet
Temp
(F)
31 Temp. rise across the exchanger (don’t exceed 35°F, 19.4°C)