SEE FIG. 10 & 11
1. Check that the hearth is level, then remove the
appliance from its transit wooden pallet.
2. Lift up the insulating covers and remove the hotplate
using lifting hooks provided.
3. Connect and terminate flue system in accordance with
the regulations in force.
Refer to Section ‘BALANCED FLUE INSTALLATION’ for
terminal kit installation details.
4. Remove the 4 flue cleaning access door securing bolts
and remove door.
5. Check the position of the boiler flueway baffles.
6. Replace door and refit bolts.
7. Replace the hotplate ensuring that it seals around the
edges.
NOTE
The baffles are assembled in alternate directions to allow
the gases to flow front to back through the assembly.
Each heat exchanger has two rows of baffles .
Ensure that the baffles are having the top and bottom
plates of the same width and marked
TOP
are fitted last.
One at top of each flueway.
Total number of baffles fitted:-
440 = 6
(2 x 3)
460 = 6
(2 x 3)
480 = 8
(2 x 4)
499 = 10
(2 x 5)
Installation requirements
18
SITE LOCATION
Fig. 10
Fig. 11
DESN 510523
DESN 512011
Summary of Contents for Heatranger 440
Page 14: ...Site requirements 440 460 480 499KB EXTERNAL CONTROLS 14 ...
Page 16: ...16 Site requirements Fig 7 WIRING DIAGRAM 440 460 480 499 KB ...
Page 19: ...Installation requirements Fig 12 19 ...
Page 25: ...Sealed System 25 Fig 21 ...
Page 41: ...41 ...
Page 42: ...42 ...
Page 43: ...43 ...